Clutch Engagement / Electronic Control System Test (Fig. 8)
This test can be used to check for proper operation of
the electronic control system and clutches without con
necting the machine to a water source or operating the
machine.
1. Park machine on a level surface, stop the engine,
engage the parking brake, open the hood and discon
nect the engine spark plug wires.
2. Disconnect wiring harness connector from bottom of
water pressure gauge. Install a jumper wire across
terminals of disconnected wire connector. This will elec
trically by-pass the water pressure switch.
3. Turn ignition key switch to ON position. DO NOT start
the engine.
4. ENGAGE test:
A. Lower machine to aerate position (on rollers).
Yellow light should be ON.
B. Move traction bail out of neutral. Red light should
come ON.
C. With traction bail out of neutral, push, then re
lease, green aerate ENGAGE button. Green light
should come ON and pump clutch should engage.
After 5 seconds valve clutch should engage.
NOTE: Touch clutches with a metal object, such as
a screw driver, to help check for clutch engagement
(clutch will be magnetized).
5. NEUTRAL shut-down test:
A. Release traction bail. Red light should turn OFF.
B. After 4 seconds, pump clutch should disengage
and green light should go OFF.
C. After another 3 seconds, valve clutch should
disengage.
6. DISENGAGE test:
A. Move traction bail out of neutral and push green
aerate ENGAGE button.
B. After clutches are engaged, push red aerate
DISENGAGE button.
C. Green light should immediately turn OFF and
pump clutch should disengage.
D. After 3 seconds, valve clutch should disengage.
E. System must not restart without pushing green
aerate ENGAGE button.
IMPORTANT: When test is completed, water pres-
sure switch by-pass must be removed to prevent
damage to water system from low inlet water pres-
sure.
7. Remove by-pass jumper wire that was connected in
step 2 and connect wire harness connector to terminals
on bottom of water pressure gauge.
Figure 8A
3
2
1
1. Red light
2. Green light
3. Yellow light
Figure 8B
1. Red light
2. Green light
3. Yellow light
Testing
Page 5 - 16
Hydroject 3010
Summary of Contents for HydroJect 3010
Page 2: ...Hydroject 3010...
Page 4: ...Hydroject 3000 4000...
Page 10: ...Equivalents and Conversions Product Records and Maintenance Page 2 2 Hydroject 3010...
Page 44: ...Repairs Page 4 26 Hydroject 3010...
Page 72: ...Repairs Page 5 28 Hydroject 3010...
Page 102: ...This page is intentionally blank Repairs Page 6 28 HydroJect 3010...
Page 109: ...IRXU ORFDWLRQV 7RUTXH WR IW OE LJXUH GURMHFW 3DJH 5HSDLUV...
Page 118: ...This page is intentionally blank Electrical Diagrams Page 8 2 Hydroject 3010...
Page 119: ...Page 8 3 Electrical Schematic Hydroject 3010...
Page 120: ...Hydroject 3010 Main Harness Page 8 4...
Page 121: ...Page 8 5 Main Wiring Diagram Hydroject 3010...
Page 122: ...Hydroject 3010 Control Panel Harness Page 8 6...
Page 123: ...Hydroject 3010 Tiller Wire Harness and Diagram Page 8 7...
Page 124: ......