63
Pre-Field Acceptance Test
TORNATECH MODEL GPX
WITH OR WITHOUT GPU TRANSFER SWITCH
ELECTRIC FIRE PUMP CONTROLLER
PRE- FIELD ACCEPTANCE TEST
CHECK LIST
Note: This document should be an official indication of whether or not the installation and general condition
of the equipment is adequate for a field acceptance test. This document should also aid the individual
responsible for executing the field acceptance test to decide whether or not to carry out the field acceptance
test of the equipment.
Installation Check List:
YES
NO
1
Verify that the nameplate of the Fire Pump Controller (and Transfer Switch if supplied)
corresponds with the AC voltage available.
2
Visual inspection for any damage to the exterior of the Fire Pump Controller. Make sure
the enclosure, alarm bell, selector switch, membrane and display are not damaged.
3
Verify that the Fire Pump Controller has been installed within sight of the pump and engine
or motor.
4
Verify that the Fire Pump Controller has been installed not less than 12 inches from the
floor of the mechanical room.
5
Verify that all electrical connections to the Fire Pump Controller are done using liquid tight
conduit and connectors.
6
With the Fire Pump Controller door open, visually inspect for any drill chips, dirt or foreign
objects in the bottom of the enclosure, loose wires, broken components and general
proper electrician workmanship.
7
Verify that the correct Normal Power AC voltage is supplied to the controller by taking a
voltage reading at the incoming terminals of the isolating switch (IS).
8
If applicable, verify that the correct Alternate Power AC voltage is supplied to the controller
by taking a voltage reading at the incoming terminals of the alternate power isolating
switch (AIS).
9
Verify that the motor leads are connected for the corresponding starting method.
Initial Power-Up Check List:
YES
NO
1
Controller door must be closed and latched with Normal Power Disconnecting Means
handle in the OFF position. If a Transfer Switch is supplied, its door must be closed and
latched with the Alternate Power Isolating Switch handle in the OFF position.
2
Verify that the Emergency Start Handle is in the OFF position.
3
Place the Normal Power Disconnecting Means handle in the ON position. If a Transfer
Switch is supplied, place the Alternate Power Isolating Switch in the ON position.
4
Verify that the Normal Power voltage and hertz displayed on the digital screen are the
same as measured in point 7 of the Installation Checklist above.
5
Verify that the Alternate Power voltage and hertz displayed on the digital screen are the
same as measured in point 7 of the Installation Checklist above.
6
Verify that there is no Phase Reversal Alarm on both the Normal Power and the Alternate
power side.
Note: A manual or automatic start must only be executed if the motor and the pump have
been cleared to be started by their respective official service technicians.
YES
NO
1
Place the Normal Power Disconnecting Means handle in the ON position. If a Transfer
Switch is supplied, place the Alternate Power Isolating Switch in the ON position.
2
Push the START pushbutton. The motor will start.
3
Verify the motor rotation on both normal power and alternate power if applicable.
• If the motor rotation is correct, no adjustment is required.
• To correct the motor rotation, change the motor connection leads 1 and 3 (A and C) at
the run contactor
4
Verify any alarms that would appear on the digital display screen. Correct any alarm
condition.
5
Set the Cut-Out and Cut-In settings by following the ViZiTouch documentation. You need
to be logged in to modify these settings. Verify the automatic start by dropping the system
pressure below the Cut-In setting.
6
Stop the motor by pressing the “STOP” membrane button. Note: the motor will only stop if
Summary of Contents for GPU