2.4 Tools
Tube Cutter
Tools for stripping of cable, loose tube and fiber
Screwdriver
3 Installation of the TCB-O
3.1 Preparation
Before installing the TCB distribution box on the wall, please
mark the recommended minimum space requirement of
approx. 1,200 x 550mm (H x W). The distance to the ceiling
should not be less than 200mm if possible to provide safe
access to the screwing of the Entry box cover.
The left starting position of the distribution box depends on
the cable routing from the ceiling, or from the side so that
these can be inserted into the entry box on the left side,
taking into account the minimum bend radius.
If cables from the subscriber or the operator are already in
place for later termination in the distribution box, ensure that
they have sufficient space for safe installation.
3.2 Installation
Take the keys for the locks at the cover and unlock the
locks. Remove the cover and set it aside.
Loosen the two screws on the cover of the entry box only
until you can remove the cover. Also place the cover to the
side and tighten the screws slightly so that they are not lost.
Unlock the cover of the patchfield box with the key and open
the hinged cover.
To open the pivotable tray holder, you must unlock the bolt
at the top.