3
|
Installation Environmental Considerations
14
|
Orion 2295 Phosphate Analyzer
Thermo Scientific
Section
Section
Plumbing Connections
Sample inlet, sample return and drain connections are made on the bottom side of the
instrument. The sample inlet and sample return fittings on the bottom of analyzer require
¼" OD (6 mm OD) flexible tubing. The drain fitting at the bottom of the analyzer requires
⅜
" OD (9.6 mm OD) flexible tubing. The air purge inlets require ¼" OD tubing. The air purge
supply must be filtered externally and free of oil and any other particulates.
Figure 5: Internal tubing and tube routing
interconnections
NOTES:
1. It is recommended that you install an external sample shut off valve
to allow control while accessing or service to the sample chamber.
2. Air purging of upper and lower enclosures is recommended.
3. Each analyzer MUST have its own drain tube vented to atmosphere.
4. The installation of a power circuit breaker is highly recommended.
DANGER
The
⅜
" (9.6 mm)
DRAIN MUST BE VENTED TO ATMOSPHERE
. The sample
drain contains analysis wastes, which include both sample and chemical
reagents. Please check with local authorities concerning proper disposal of
waste from this product.
NOTES:
The enclosure drain produces no waste under normal use. However, in the
event of spills or leaks, some waste may be produced.
The analyzer is shipped with all of the internal tubing attached. Before starting
up the instrument, verify that the tubing lines are secured.