Maintenance
Preventive Maintenance Schedule
(Page 2)
Weekly/Routinely
All
Inspect Drum and Drive
Motor and Coupler
Assemblies
Inspect drum, drive motor and coupler for obvious signs of
damage, and loose or missing bolts/screws/parts. If damage or
loose, do not operate machine, as service may be required.
All
Inspect Trailer Axle
Assembly
Inspect for alignment, broken or damaged spring leaves.
All
Inspect Axle Drum Oil
Level
Fill to just below drum plug- (
see Axle Drum Oil section).
All
Check Battery
For proper charge.
All
Check Tire Inflation
Check tire air pressure-
(see Tires section)
.
All
Open Evacuator Valve on
Engine Air Filter Housing
Open the evacuator valve on the engine air filter housing to
purge any large particles of dust or debris.
Every 50 Hours of Use or 3 months/3,000 miles
(whichever comes first)
All
Inspect Tire Condition
Inspect tires for wear and damage every 3 months/3,000 miles-
(
see Tires section).
All
Check Torque on Wheel
Nuts and Bolts
Tighten to specified torque values every 3 months/3,000 miles-
(see Trailer Wheels section).
All
Adjust Trailer Brakes
Every 3 months/3,000 miles-
(see Brake section).
All
Inspect Fuel Lines and
Clamps
Inspect all fuel lines from for damage/leaks. Also, inspect fuel
line hose clamps and ensure they are tight.
PT-7500
Drain the Fuel Water
Separator
(If Applicable)
Drain the fuel water separator to purge any
accumulated water from the diesel fuel lines.
WARNING:
System must be tagged/locked out prior to removing any machine guarding, removing any system
component, or performing any maintenance outside of basic visual inspections.
NOTE:
All preventive maintenance steps detailed in this sections are in addition to the required pre/post-
operation inspection steps.
NOTE:
All Preventive Maintenance should be conducted in accordance with OSHA requirements, to include OSHA
Standard- 29 CFR, Part 1910.147.
Summary of Contents for PT-3500
Page 1: ...PT 3500 PT 7500 Puller Tensioner Operators Manual...
Page 2: ......
Page 6: ......
Page 9: ......
Page 81: ......
Page 83: ...S R Revolution Series PT 3500 PT 7500 Puller Tensioner Page 79 Troubleshooting...
Page 84: ...S R Revolution Series PT 3500 PT 7500 Puller Tensioner Page 80 Fuse Relay Wiring Schematic...
Page 89: ......
Page 129: ...Revolution Series PT 3500 PT 7500 Puller Tensioner Page 121...
Page 131: ...Revolution Series PT 3500 PT 7500 Puller Tensioner Page 123...
Page 133: ...Revolution Series PT 3500 PT 7500 Puller Tensioner Page 125...
Page 134: ...Revolution Series PT 3500 PT 7500 Puller Tensioner Page 126 A...