3.
On the DK-LM3S9B96 board remove the shunt jumpers on JP16-JP31 and the JP39 headers
as shown in Figure E-1 on page 41.
Figure E-2.
Removing EPI Board from DK-LM3S9B96 Development Board
4.
Install the two snap-in nylon standoffs on mounting holes above the EPI connector J2.
5.
Place the expansion board on top of the DK-LM3S9B96 board and align the standoffs, the EPI
connector, and the 2x17 J2 header.
6.
Press firmly downward until the board snaps in, then verify that the board is firmly seated on
the EPI connector, the 2x17 header, and the standoffs.
7.
When powering up the board, verify that the power indicator LED D1 is lit.
Remove board
Remove jumpers
Summary of Contents for Stellaris LM3S9B96
Page 20: ...20 September 5 2010...
Page 22: ...22 September 5 2010...
Page 24: ...24 September 5 2010...
Page 32: ...32 September 5 2010...
Page 34: ...34 September 5 2010 Figure B 1 Component Placement Plot for Top...
Page 36: ...36 September 5 2010...
Page 40: ...40 September 5 2010...
Page 68: ...68 September 5 2010...
Page 80: ...80 September 5 2010...