CommIssIonIng
41
© TESVOLT We reserve the right to make technical changes! RD.TI.026.E.ENG_Installation_Manual_TSHV70OD_v.A.01 Last revised
07/2020
15
The 125 A NH00 fuses
9
or
37
(see “5.8 Connector panel” on
page 19 et. seq.) for the battery inverter can now be inserted in
the left fuse holder. To do this, open the left fuse holder and push
the fuses into the relevant slot parallel to the holder. Then close
the fuse holder.
16
Once the NH00 fuses have been inserted, wait until the SMA STPS 60 has completely started up.
17
The TS HV 70 Outdoor switches to “INIT” mode and the switch
starts to flash.
18
The commissioning process for the SMA STPS 60 must then be
started using the SMA LCS Tool. The software and a manual can
be found on the USB drive
11
.
Once the commissioning process
has been successfully completed, all the TS HV 70 Outdoor units
switch to pre-charge mode “PRECH”.
19
Once the precharging has completed successfully, the switches in
all the APUs in the master/slave arrangement are permanently
illuminated. “OK” appears as the Status item on the display. All
the TS HV 70 Outdoor units are now ready for operation.
Note:
The display remains active for approximately two minutes and is then deactivated. It can be
reactivated by tapping twice.
20
Close the connector panel on the STPS. Then refit the cover
I
and lock using the key
T
.