The loads of 2400 Pa, 3800 Pa and 5400 Pa are under IEC standard. The installation 

methods applicable for 5400 Pa are also relevant for 3800 Pa and 2400 Pa. The installation 
methods applicable for 3800 Pa are also relevant for 2400 Pa. 

**    

The module clamps must not come into contact with the front glass or deform the 

frame in any way. Avoid shading effects from the module clamps and insertion systems. 
Drainage holes in the module frame must not be closed or obscured by the clamps. 

***    

 Measurement A stands for the distance from the module edge to the clamping 

zone. Measurement A is 150mm for T series 35 mm thickness, 180mm for W series 35mm 
thickness, 280mm for V series 40mm thickness. The clamping zone defines the range for the 
middle point of the clamp.

5400 Pa Load * 

5400 Pa Snow Load

3800 Pa Wind Load

Clamping sy

stem

 

**

Attachment to the long frame

Use four clamps

 

 

Clamping Zone

(160mm) 

A***

A***

A***

A***

The loads of 3800 Pa and 5400 Pa are under IEC standard. The installation methods 

applicable for 5400 Pa are also relevant for 3800 Pa and 2400 Pa. The installation methods 
applicable for 3800 Pa are also relevant for 2400 Pa. 

**    

The module clamps must not come into contact with the front glass or deform the frame in 

any way. Avoid shading effects from the module clamps and insertion systems. Drainage holes in 
the module frame must not be closed or obscured by the clamps. 

***    

 Measurement A stands for the distance from the module edge to the clamping zone. 

Measurement A is 320 mm for AC module. The clamping zone defines the range for the middle 
point of the clamp.

Suntech W series AC module

Electrical Installation

General installation

• 

Any hardware used must be compatible with any other used material to avoid 

galvanic corrosion. Defects caused by corrosions void the warranty.
• 

It is not recommended to use modules with different configurations (grounding, 

wiring) in the same system.
• 

Excessive cables must be organized or fixed in an adequate way, e.g. attached to 

the mounting structure by using non-metallic cable ties.

 

Solar cables, connectors and 

juction boxes should not be exposed to water exposure, and snow, and rain or water 
submersion for a long period of time(IP65/67).
• 

For applications requiring high operating voltage several modules can be 

connected in series to form a string of modules; the system voltage is then equal to the 
sum of the voltage of each module.
• 

For applications requiring high operating currents several strings of modules can 

be connected in parallel; the system current is then equal to the sum of the current of 
each string of modules.
• 

The maximum system voltage is 600 volts or 1000 volts depending on the product 

family DC according to standards. 
• 

The maximum number of series connected modules depends on system design, 

the type of inverter used and environmental conditions.
• 

Based on the maximum series fuse rating of module and local electrical installation 

code, always make sure Suntech PV modules with more than two strings in parallel for 
connection are assembled with the appropriate string fuse for circuit protection. 
• 

There is no limitation on the number of modules that can be connected in parallel, 

the number of modules is determined by system design parameters such as current or 
power output.
• 

To prevent the cables and the connectors from overheating, the cross section of 

the cables and the capacity of the connectors must be selected to suit the maximum 
system short circuit current. The recommended cable is PV wire with a cross section of 
at least 4mm

2

.

• 

Caution: do not metalize the cables too tight.  Any cable damage caused by cable 

management system is not covered under Suntech's warranty.
• 

Always refer to the cable manufacturer's bending radius which includes the radius 

just behind the connectors.

No.12

No.11

Summary of Contents for STP185S-16/Tem

Page 1: ......

Page 2: ... General installation Installation method Attachment guidelines 11 Electrical Installation General installation Grounding 14 Maintenance No 1 Global Installation Guide for Suntech Power Photovoltaic Module Version 20150101 Please read carefully This document is binding for any warranty case Any installed PV system less than 500m from coastline please refer to the Near coast installation manual ...

Page 3: ...d to as module Wuxi Suntech Power Co Ltd referred to as Suntech Installers must read and understand this guide prior to installation For any questions please contact Suntech s Global Quality Customer Support department or our local representatives for more detailed information Installers must follow all safety precautions as described in this guide as well as local requirement and regulations by l...

Page 4: ...ling mechanical and electrical components Completely cover the module with an opaque material during installation to prevent electricity from being generated Do not wear metallic rings watchbands earrings nose rings lip rings or other metallic objects while installing or troubleshooting photovoltaic systems Follow the safety regulations eg safety rules for working on electrical power plant station...

Page 5: ... of 10 cm between the roof plane and the frame of the module is generally recommended Always observe the instructions and safety precautions included with the module support frames No 6 This installation manual is applicable for all pv system of 500 m or more away from the coastline If you need to install your system less than 500m from the coast line please refer to Near coast installation manual...

Page 6: ...es W series V series module No 9 2400 Pa Load 2400 Pa Wind Load 2400 Pa Snow Load 3800 Pa Load 3800 Pa Wind Load 3800 Pa Snow Load 5400 Pa Load 5400 Pa Snow Load 3800 Pa Wind Load Mounting system Clamping system Attachment to the long frame Length Use four clamps Use four clamps Use six clamps Clamping system Attachment to the short frame Use four clamps on short frame Use four clamps on the short...

Page 7: ... void the warranty It is not recommended to use modules with different configurations grounding wiring in the same system Excessive cables must be organized or fixed in an adequate way e g attached to the mounting structure by using non metallic cable ties Solar cables connectors and juction boxes should not be exposed to water exposure and snow and rain or water submersion for a long period of ti...

Page 8: ...al hand over to the owner including an installation protocol is required Provide a clear documentation of the system to the owner consisting of following minimum data such as user guide system layout data sheets performance expectations electrical system data e g a copy of the installation test report following minimum requirements of IEC 62446 IEC 60364 6 Grounding For grounding and bonding requi...

Page 9: ...ix months to verify that they are clean secure undamaged and free of corrosion Or else the warranty may be voided In the event of a ground fault condition NEVER wash or spray modules with water until ground fault has been identified corrected by an authorized solar inverter service technician and the inverter is fully operational This can cause electrocution or a serious safety issue If any proble...

Page 10: ... 1000 600 20 STP265 20 Wem 31 0 8 56 37 8 9 02 265 1000 600 20 STP260 20 Wem 30 9 8 42 37 7 8 89 260 1000 600 20 STP255 20 Wem 30 8 8 28 37 6 8 76 255 1000 600 20 STP250 20 Wem 30 7 8 15 37 4 8 63 250 1000 600 20 STP275S 20 Wem 31 1 8 85 38 5 9 34 275 1000 600 20 STP270S 20 Wem 30 8 8 77 38 3 9 28 270 1000 600 20 STP265S 20 Wem 30 5 8 69 38 1 9 22 265 1000 600 20 STP260S 20 Wem 30 2 8 61 37 9 9 17...

Reviews: