7. INSTALLATION OF THE HEATING
STOVE
7.1.Connecting the stove to a chimney
Stove-to-chimney
connection
must
always comply with the existing standards
and rules. The chimney must provide
sufficient draught for evacuation of the
smoke under any conditions.
The proper functioning of the stove
requires adequate sizing of the chimney
itself since the draught it produces affects
combustion, boiler’s output and life span.
The draught created by the chimney is
in functional relation to its cross-section,
height and the roughness of its interior
walls.
No other appliance may be
connected to the chimney serving the
stove.
Chimney diameter must not be
smaller than the flue outlet of the stove.
Flue outlet must be connected to the
chimney opening. In terms of mechanical
properties, the flue outlet must be sturdy
and properly sealed (to avoid gas leak)
and allow for easy access for cleaning
on the inside. The inner section of the
flue outlet must not be greater than the
effective section of the chimney and must
not narrow. Avoid using elbow joints.
The chimney cleaning opening has to be
in its lowest part. The chimney’s wall has
to be three plied where the medium layer
is from mineral wool. The thickness of the
insulation is not less than 30 mm when
the chimney is setting up inside the house
and the thickness is 50 mm, when the
setting up is outside.
The internal flue diameter depends on its
actual height and the stove rated power
(see Table 4).
Please entrust choosing a chimney and its
installation by a qualified professional.
The required distance between the
boiler and the chimney is 300-600 mm.
Scheme 2. Connect the pellet stove with a
chimney
Table 4. Recommended minimum sizes and
chimney draft
Stove
output
Chimney
diameter, mm
Chimney draft, Pа
8 kW
Ø 80 мм
10
10 kW
Ø 80 мм
10
Summary of Contents for BURNIT AMBIENT V2 4G 10 Plus
Page 18: ...18 TECHNICAL PASSPORT INSTALLATION and OPERATION MANUAL...
Page 20: ...20 TECHNICAL PASSPORT INSTALLATION and OPERATION MANUAL 9 2 Controller Menus...
Page 22: ...22 TECHNICAL PASSPORT INSTALLATION and OPERATION MANUAL...
Page 32: ...ISO 9001 2008 BUREAU VERITAS Certification tel 359 700 17 343 www burnit bg...