7 System Debugging
7.1 Inspections Before Power-On
No.
Inspection items
Acceptance criteria
Validation
1
The energy storage is installed
in place
The installation is correct, secure and reliable.
□Yes
□No
2
The installation environment
meets requirements
The installation space is reasonable and the
environment is clean and tidy without any construction
remains.
□Yes
□No
3
The power cord is correctly
connected
The positive and negative terminals are connected
correctly without any missing.
□Yes
□No
4
The signal line is correctly
connected
The signal line is connected reliably, and there is no
wrong position
□Yes
□No
5
The grounding is reliable
The grounding wire is correctly and reliably connected.
□Yes
□No
6
The switch of the energy
storage battery module is off
All switches connected to the energy storage are in the
"OFF" state.
□Yes
□No
7
All breaker of the battery
module are off
All breaker of the battery module are in the "OFF" state.
□Yes
□No
7.2 Power-On of Power Module
7.2.1 Inverter Breaker Sequence
First, Turn on the battery input breaker switch; then turn on the PV, AC output and AC input breaker switch.