FOUNDATION

 

SMART STORE WOODEN FLOOR 

 

 

• 

The optional Smart store kitset wooden floor is precut and de-
signed to be fitted into the shed after the shed is assembled.

 

 

 

• 

Assemble shed as per  instructions and fit floor last.

 

          (see page 13 for details). 

 

CONCRETE SLAB FOR RAISED BASE PLATE SHED

 

 

To build a raised concrete slab for your shed to sit on, we recom-

mend the following:

 

 

• 

The raised slab size should be 15mm smaller than the base 
size of the shed and at least 30mm above ground line.

 

 

• 

The slab should be 80mm thick in the middle and 100mm 
thick around the edges.

 

 

• 

The slab should be laid on a solid or compacted base.

 

 

• 

Plastic sheeting under slab will prevent moisture coming 
through from underneath

.

 

 

• 

During construction, you may raise the  bottom timber 
plate to allow the wall cladding to protrude 20mm below 
the bottom plate. This will stop water flowing between 
the bottom plate and the concrete floor. 

 

          

See note on page 8.

 

80mm

 

100mm

 

7.5mm

 

20mm

 

Concrete Floor

 

Base Plate

 

Wall Cladding

 

6

 

RAISED BASE PLATE OPTION

 

(For sheds placed on a raised concrete floor)

 

No doubt by now you will have decided what sort of base you are putting down. 

 

Please read the section that applies to your situation.

 

If you choose to pour a concrete base you will need to decide whether you wish to raise the base plate of your shed. 

This allows the cladding to protrude below the surface of the concrete and ensures a water tight pad. 

 

See concrete pad specifications below

 

By choosing this option you will need to make the concrete pad to the specification below.

 

Summary of Contents for SM3015

Page 1: ...ASSEMBLY INSTRUCTIONS SM3015 BASE SIZE 3 020m x 1 520m...

Page 2: ......

Page 3: ...cess needs to be adhered to to qualify for the steel warranty of your Duratuf Smart store shed Wash all surfaces annually using a hose and soft nylon brush Within 2 km of coast wash every 3 months as...

Page 4: ...gle 1 935m 2 Side Wall Angle 1 905m 2 Roof 1 720m 6 Door Sheet Narrow 1 940m 3 Door Sides 1 940m 4 Door Jamb 1 980m 2 Door Brace 1 200m 2 Door Brace 0 955 2 Weatherstrip 1 940 1 Barge 1 720m 2 Door To...

Page 5: ...PACK 2 TIMBER DESCRIPTION QTY DIAGRAM Front Back Bottom Plates H4 Green 3 020 m 2 Front Back Top Plate H1 Red 3 020 m 2 Side Wall Bottom Plates H4 Green 1 520 m 2 Side Wall Top Plates H1 Red 1 522m 2...

Page 6: ...LE BACK PANEL 1 LAY FOUNDATION 2 ASSEMBLE DOOR QUICK OVERVIEW 3 ASSEMBLE SIDE PANELS Top Plat Barge Flashing Spouting Roof Sheets Top Plate Side Top Plate Front Bottom Plate Bottom Plate Front Wall Do...

Page 7: ...ng through from underneath During construction you may raise the bottom timber plate to allow the wall cladding to protrude 20mm below the bottom plate This will stop water flowing between the bottom...

Page 8: ...ans are on the outside Rivet sheets together ensuring ends are flush with each other STEP 2 Position door side flashings and 0 945m top and bottom flashings and assemble door as shown ensuring narrow...

Page 9: ...with bottom of sheets flush with each other Rivet sheets together on overlaps as shown STEP 3 Nail wall sheets to the Top Plate at each end making sure that the top of the sheets are flush with the t...

Page 10: ...sing two clouts per pan STEP 4 Nail the wall sheets to the Bottom Plate at each end ensuring that each side of the wall sheets overhangs the Bottom Plate by 15mm and that the distance between the Top...

Page 11: ...correct distance apart and that the sides of the wall sheet overhang the Bottom Plate by 15mm Drill rivet Door Jamb Flashings to wall sheets using four riv Plan View STEP 2 Using 2 x 30mm clouts nail...

Page 12: ...Using 2 x 40mm screws screw Top Plates together in the corner Using 2 x 40mm screws 2 per join screw the Bottom Plates together in the corner STEP 2 Repeat Step 1 with the second Side Panel ensuring...

Page 13: ...all Sheets fig 2 STEP 3 Ensure the Front and Back Top Plates are straight Screw the roof sheets to the front back Top Plates using 1 x Roofing Screw per rib fig 2 STEP 4 Place barge flashings on roof...

Page 14: ...N CORROSION AND COULD THEREFORE VOID THE WARRANTY FIT PADBOLT Rivet Padbolt to door and keeper onto Door Jamb as shown 13 YOUR DURATUF SMART STORE SHED IS NOW COMPLETE RELAX FITTING A SMART STORE FLOO...

Page 15: ......

Page 16: ...s less than 200g m2 as published by Branz Warranty certificate being returned to manufacturer within 21 days of purchase together with proof of purchase This warranty does not cover the following Fast...