Section 3 - Operation
3.10-2 Locking the Turret
1.
Ensure that turret is positioned so that turret
transportation lock tube (
item 1 - Figure 3-7
) is
aligned into one of two turret locking points in the
turret rotation lock plate.
2.
Pull out turret lock retaining pin (
item 2 - Figure 3-7
).
Lower turret lock into locked position and reinsert
turret lock retaining pin.
3.10-3 Lifting
NOTE
When it becomes necessary to lift aerial
platform, it is very important that lifting
devices are attached only to designated
lifting points (refer to
Figure 3-8
).
WARNING
Use chains of ample load capacity
sufficient to withstand aerial platform
weight.
1.
Place boom in stowed position centered
between drive wheels. Lock turret using turret
transportation locking pin (refer to
into the transport point (refer to
Figure 3-7
).
2.
Turn main power disconnect switch to “
” off
position.
3.
Remove all loose items from aerial platform.
4.
Properly adjust rigging to prevent damage to aerial
platform and so aerial platform remains level.
Figure 3-7. Turret Transportation Lock & Locking Points
Figure 3-8. Lifting Points
NOTE: Center of gravity varies with different options.
Transport Point
2
1
53”
53”
X
CL
X
= 9 ” (230 mm)
46AJ
(1346 mm)
(1346 mm)
Summary of Contents for SJ 46AJ
Page 1: ...ARTICULATING BOOMS MODELS SJ46AJ 169510AD A November 2015 OPERATING MANUAL ANSI CSA ...
Page 12: ...Page 12 December 2007 SJ 46AJ Notes ...
Page 62: ...Page 62 December 2007 SJ 46AJ Notes ...
Page 92: ...Page 92 December 2007 SJ 46AJ Notes ...
Page 94: ...www skyjack com Pålitelig lift løsninger av folk som bryr seg ...