Installation and initial start-up
Initial start-up
Perform the installation check before you start up the telescopic pillar for the first time
TFG.
Installation check
Check the following points before the initial start-up:
■
All instruction points from the above sections of this chapter carried out
■
Grounding conductor resistance and substitute leakage currents checked
■
No impermissibly high side-acting forces impacting on the guide tubes
■
Fastening screws secured on inner, outer and push tubes
■
Entire stroke area not obstructed, so that the pillar cannot be driven onto a fixed
object
■
All cables secured against pinching and trapping, and properly connected
■
Electrical supply secured
■
Magnetic operating element connected to the control unit
Initial start-up
After the installation check has been completed, you can start up the telescopic pillar
TFG: To do so, press the corresponding operating button of the SKF operating element.
WARNING
Warning for risk of crushing and damage to the TFG caused by stat-
ic and dynamic overloading of the telescopic pillar. When driving
against fixed objects the impact of the force can cause personal in-
jury. Make sure that there are no persons or fixed objects present
in the danger zone during the stroke.
•
Note the maximum permissible operating data in the Appen-
dix (see
•
Note the type plate of the telescopic pillar
!