Proceed with the initial start-up in accordance with the following table:
WORKSTEP
ADDITIONAL INFO / IMAGES
1.
Check whether all components are correctly
mounted and connected.
Section 4
2.
If pumps are present, then check that they are
connected to earth.
3.
Remove the cover on the measuring cell and
check that the optics are clean.
Section 9.4, Section 9.6 and Sec-
tion 9.7
4.
Ensure that the sample return is in place.
4.1: Open the outlet valve at the customer (Figure
7, pos. Y).
4.2: Fully open the needle valve (C) on the pump.
4.3: Fully open the ball cock (B) on the pump.
4.4: Open the pressure reducing valve (A) slowly
until the pump starts to operate minimally.
4.5: Increase the pressure on the pressure reduc-
ing valve (A) by 0.5 bar.
4.6: Carry out fine tuning of the pump output on
the needle valve (C) in order to optimize the air
consumption of the pump.
5.
If optional sampling equipment is present, then
open the outlet valve here (Figure 7, pos. 5).
6.
6 a) Setting up the sample feed without a
pump.
6.1 a: If an optional sample preparation system is
present (Figure 7, pos. 1), then remove the cover
here.
6.2 a: Ensure that the drainage valve is closed
(Figure 7, pos. 2).