3. Make the following settings in the "Extended load" dialog:
– PG/PC interface: Network card used, e.g. "Intel[R] Ethernet Connection I217-V"
– Connection with interface/subnet: Specific interface on the SINUMERIK MC or "Try all
interfaces"
4. Click on "Start search" and then select the PLC that was found from "Compatible nodes in
the target subnet".
Alternatively, you can specify an IP address directly in the "Compatible nodes in the target
subnet" list in the "Address" column.
5. Click on "Load" to confirm the load operation.
Dialog "Load preview" opens.
Figure 6-8
Load preview
Note
Consistency check
Before the loading, the consistency of the download is checked. This means that a check is
performed as to whether the parameterized hardware of the TIA Portal project matches the
hardware that has actually been installed.
Note
Adapt the IP address?
If the IP address of your PG/PC is located in a different subnet than the PLC, a dialog box
is displayed as to whether the IP address in the PG/PC should be adapted.
6. Check the settings in dialog "Load preview". Click "Load" to confirm the entry.
Commissioning and configuring
6.4 Load the configuration into the control system
Safety Integrated (with SINAMICS S120)
244
Commissioning Manual, 02/2020, A5E46305916B AB