3-1
MP270 Equipment Manual
Release 01/99
Commissioning
Flowchart
The following information on commissioning explains the individual steps which
need to be taken to start up the MP270. Figure 3-1 illustrates the most important
steps for the initial startup, recommissioning and normal operation of the MP270.
Download configuration data to the MP270
COM1/2
During the start-up phase, switch the
MP270 to download mode (refer to
Page 3-3)
Switch on the MP270’s power supply.
Initial startup
There is no configuration
available in the MP270.
Recommissioning
The MP270 already contains
a configuration but needs to
operate with a different one.
Normal operation
The MP270 is operated with
the configuration which is
currently loaded.
Start screen
PC/PU
MP270
Figure 3-1
Commissioning flowchart
3
Summary of Contents for Multi Panel MP270 SIMATIC HMI
Page 8: ...Preface vi MP270Equipment Manual Release01 99 ...
Page 18: ...Functionality 2 4 MP270EquipmentManual Release01 99 ...
Page 36: ...MP270 Operation 4 14 MP270Equipment Manual Release01 99 ...
Page 64: ...System Settings 6 8 MP270Equipment Manual Release01 99 ...
Page 82: ...Unit Description 8 8 MP270Equipment Manual Release01 99 ...
Page 90: ...Maintenance Upkeep 10 4 MP270Equipment Manual Release01 99 ...
Page 92: ...APPENDICES J 2 MP270Equipment Manual Release01 99 ...
Page 98: ...Technical Data A 6 MP270Equipment Manual Release01 99 ...
Page 114: ...System Messages C 14 MP270Equipment Manual Release01 99 ...
Page 144: ...Index Index 8 MP270Equipment Manual Release01 99 ...