Commissioning
5
5.1
Overview
Prerequisites
1.
The device has been installed.
2.
The device has been connected in accordance with the possible connection methods.
3.
The RS485 interface has been connected to the bus.
Note:
The RS485 interface must be connected for commissioning via the powerconfig
parameterization software.
Steps for commissioning the device
1.
Connect the supply voltage.
2.
Parameterize the device.
3.
Connect the measuring voltage.
4.
Check the displayed measured values for plausibility.
5.
Check the polarity and the phase assignment of the instrument transformers.
NOTICE
Device can be irreparably damaged
When performing an insulation test of the entire installation with AC or DC, the device
should be disconnected before starting the test.
Note
Check the connections.
Incorrect connection can result in malfunctions and failure of the device.
Prior to commissioning the power monitoring device, check that all connections are correct.
Summary of Contents for 7KM1020-0BA01-1DA0
Page 1: ......
Page 2: ......
Page 8: ...Table of contents PAC1020 6 Equipment Manual 05 2020 L1V30610008B 01 ...
Page 22: ......
Page 50: ...Operation 6 1 Device interface PAC1020 48 Equipment Manual 05 2020 L1V30610008B 01 ...
Page 77: ...Technical data 10 1 Labeling PAC1020 Equipment Manual 05 2020 L1V30610008B 01 75 ...
Page 78: ......
Page 93: ......
Page 94: ......