Schenker 100M220 Operation And Maintenance Manual Download Page 17

 

17 

This messages means that an hydraulic block of the machine occurred, and then the pumps has been  
switched off as safety procedure. In this case is suggested to perform a reset procedure and investi-
gate on the possible hydraulic origins of the problem. 
If  the  origin  of  the  problem  is  just  a  malfunctioning  of  the  signal  pressure  switch,  it  is  possible  to  
start again the unit,  activating the bypass. 
 
 
 
BYPASS WARNING  
This  message  advice  or  remember  that  the  unit  is  working in bypass mode (then some safety func-
tions are disabled).  
 
CHANGE  PUMP FILTERS 
This is a blinking messages that must be acknowledged pressing the key STOP  
This messages suggest to replace the filter of the pump group.  

 
3. Operation 
3.2. First start-up procedure  

 
The first start-up procedure is necessary to start the first time a new system,  just installed. 
The purpose of the  procedure is basically  purge out  the air from the system.  
It can be used as well after a filter replacement, or after other maintenance operations.  
Preliminary checks: 

 

Verify that all components are connected correctly.  

 

Verify that the  filters cartridges are installed.   

 

Verify that the seawater  valve, and the possible drain valve, are opened.  

 

Verify  that the reset valve is closed (lever orthogonal to the body valve) and the positioner com-
pletely unscrewed.  

 

Verify that the small gray valve on the active carbon filter is opened and the fresh water pump of 
the boat is on. 

 

Verify that the fresh water tanks are full enough  (at least 50 liters) to perform the first washing 
operations.  

                                                                                                                                                                          
Start-up procedure:  
1.

 

Open halfway the depressurization valve (45°).   

2.

 

Activate the start up procedure  throw the function of the MENU (select the specific function in 
the menu mode, exit from menu mode pushing STOP, and start the procedure pushing START). 

3.

 

Close the depressurization valve when the display shows the specific message. 

The procedure lasts about 3 minutes. It can anyway stopped anytime pushing STOP.  
After the procedure  the system is ready to start normally.  
 
 
 
 
 
 
 
 
 
 
 
 

Summary of Contents for 100M220

Page 1: ...aterial required 2 2 Components mounting 2 3 Water intake 2 4 Hydraulic connections 2 5 Electric connections 3 Operating procedures 3 1 Remote panel commands 3 2 First start up procedure 3 3 Normal op...

Page 2: ...alternative to the high pressure pumps of traditional plants utilizes the EN ERGY RECOVERY SYSTEM patented device which amplifies the pressure of common low pres sure pumps and recoup all the hydraul...

Page 3: ...15 cm Height 23 cm Dry weight 11 Kg Connections Seawater intake holder for hose int diam 20 mm Salt water outlet holder for hose int diam 20 mm Filters 5 micron 9 propylene Power supply Pump 230 VAC...

Page 4: ...n introduce inside the allen key also without remove the electric connector Turning clockwise the allen key increases the pressure shut down set whereas turning anti clockwise decrease the pressure sw...

Page 5: ...a beat issued periodi cally by the watermaker unit The unit is constituted of 2 cylinders and a central body containing the hydraulic valve necessary for the system functioning Manometer It is locate...

Page 6: ...lever The valve must be closed during normal functioning lever perpendicular to the valve Such valve has the function to allow the reset in case of a system block It must be opened be fore acting on t...

Page 7: ...p outlet and the watermaker inlet It is fitted with a 5 microns cartridge and protects the watermaker unit from sediments and de bris CA filter white It removes the chlorine from the washing fresh wat...

Page 8: ...necessary to create a suitable wooden or fiberglass structure for the unit if an existing one not available The base of the pump is equipped with vibration damping devices but avoid installing it on...

Page 9: ...d over Allow a minimum on off ball valve on the water intake The hose connections especially if under the seawater level must be secured with double hose clamps It is not advisable to Tee into the eng...

Page 10: ...ection that is continuously under consistent pressure is the pump outlet 5 m filter watermaker inlet connections For this section is necessary to use a good quality PN 15 min rein forced hose An inade...

Page 11: ...backflow valve pump inlet pump outlet 5 microns filter watermaker inlet PN 15 reinforced hose Section 20 mm int diam Low pressure max 3 bar connection watermaker s exhaust dis charge PN 5 stainless st...

Page 12: ...pressure amplifier inside the watermaker unit marked OUT Fresh water connection The connection has to be made using the small hose furnished with the equipment and relevant endowed fittings The conne...

Page 13: ...fer ential switch requested by the local law The section of the cables will be 4 mm2 min The computer box will be powered 12 24V directly from the service batteries or through a 230 12 24 charger Conn...

Page 14: ...14 Wiring connection diagram Watermaker pressure switch Elecrovalve Batteries or charger...

Page 15: ...uddenly It awaits for the correct positioning of the internal valve 2 3 seconds and then stops automatically If the automatic washing is activated washing light on the system once pushed STOP will per...

Page 16: ...or a general service The procedure allows to purge completely the air from the system and from the seawater and the washing fresh water hoses The depres surization valve must be opened before start th...

Page 17: ...e system It can be used as well after a filter replacement or after other maintenance operations Preliminary checks Verify that all components are connected correctly Verify that the filters cartridge...

Page 18: ...Exit from the menu pushing STOP Push WASHING for 3 seconds The display will indicate the remaining day before the first rinsing The function is anyway disabled pushing STOP or after a normal producti...

Page 19: ...mix carefully following the indications on the pack Wear a protection mask in order to avoid in haling product dusts The water temperature doesn t have to be lower than 25 C preferably 3 Close the gre...

Page 20: ...acement Every 6 months Close the grey valve before open the filter Purge periodically the air from the sys tem opening at 45 for a couple of min utes the depressuri zation valve Every 15 days Check th...

Page 21: ...allation water inlet net filter Low production normal or low pressure Exhausted batteries Air in the plant Seal system leak Check battery charge Perform bleeding Contact a Schenker service point Low p...

Page 22: ...nt accessories are guarantee 12 months starting from the date on the de livery document of the merchandise The guarantee does not include expendable materials car tridges active carbon filters membran...

Reviews: