4. Installation preparations
52
© Sandvik SRP AB – Doc. no. S 223.510 en Ver. 1
CH420:01
4.3.8
Discharge arrangement
Design the discharge arrangement so that material cannot build up beneath
the cone crusher and damage the dust seal ring.
Protect the lubrication and Hydroset lines from falling material.
Concrete foundations or discharge arrangements below the cone crusher
must have an inner diameter that is larger than the cone crusher’s discharge
opening. See
The volume of the discharge area below the cone crusher must be larger than
the total volume of the process material in the cone crusher and the feed
hopper. See
If a discharge conveyor stops, the feed arrangement must also stop to allow
the process material to pass out from the crusher.
The discharge arrangement must have an inspection door for cleaning and
inspection. The Hydroset cylinder must be easily accessible.
A ledge or shelf inside the discharge compartment will absorb the impact of
the material falling onto the discharge conveyor.
Chutes should have a slope angle of at least 45° to avoid material build up. In
some cases, the inclination needs to be steeper. Contact Sandvik for further
information.
Crusher mounted on a concrete
foundation or steel supporting structure
with discharge hole in floor. Openings are
blanked off.
Crusher mounted on concrete foundation
where the foundation forms two sides of
the discharge hopper. The two remaining
sides and the hopper bottom are attached
to anchor plates cast into the foundation.
Summary of Contents for CH420:01
Page 1: ...installation manual Doc no S 223 510 SANDVIK CH420 01 ...
Page 8: ...Table of contents 6 Sandvik SRP AB Doc no S 223 510 en Ver 1 CH420 01 ...
Page 20: ...1 Introduction 18 Sandvik SRP AB Doc no S 223 510 en Ver 1 CH420 01 ...
Page 31: ...29 Sandvik SRP AB Doc no S 223 510 en Ver 1 CH420 01 3 Technical data ...
Page 109: ......
Page 110: ......