9. Preparations for commissioning
99
CH420:01
© Sandvik SRP AB – Doc. no. S 223.510 en Ver. 1
9.4 Function checks
9.4.1
Preparation
Start the cone crusher according to
OM section 4. Starting up the cone
crusher
.
9.5 Health and safety checks
9.6 Documentation
– Compile the Installation report.
List all work, besides the installation work, that was performed to
ensure correct functioning.
The installation work covered by this manual is now complete.
No.
Checks
Done
1
No unusual noises which could indicate misaligned parts or faults.
2
Hydroset pressure within limits.
4
Oil heating elements operate correctly.
5
Return lubrication oil temperature within limits.
6
Over-pressure dust exclusion system functions correctly.
7
No contact between oscillating crusher and stationary structure.
No.
Checks
Done
1
The cone crusher stops when the Emergency stop button
(if applicable) is pressed. Test must be made with the cone
crusher running.
2
The cone crusher stops when the Stop button is pressed.
3
All necessary guards are in place.
Summary of Contents for CH420:01
Page 1: ...installation manual Doc no S 223 510 SANDVIK CH420 01 ...
Page 8: ...Table of contents 6 Sandvik SRP AB Doc no S 223 510 en Ver 1 CH420 01 ...
Page 20: ...1 Introduction 18 Sandvik SRP AB Doc no S 223 510 en Ver 1 CH420 01 ...
Page 31: ...29 Sandvik SRP AB Doc no S 223 510 en Ver 1 CH420 01 3 Technical data ...
Page 109: ......
Page 110: ......