To do it proceed as follows (see figure 9):
Fix both adaptor angles "A" of the equipment as rack, to
its side by means of the supplied screws.
Put a UPS in a rack cabinet, it is needed to have the side
internal as support mode "C". In lack of them and under
request, a rails can be supplied as a guide, to be installed
by the end user. Make the assembling at the required
height, assuring the correct torque of the fixing screws.
Face the equipment over the rails and enter it to the bottom.
Depending on the model of the equipment and as a result
of the weight, it is recommended to make the installation
works by two persons, and even more when they are
done on the top and bottom of the cabinet.
Fix the equipment to the frame of the cabinet by means
of the screws "B".
4.2.5.6. 19" rack cabinet assembling, with
extended back up time (battery module).
Ŗ
This section describes a single equipment with only one bat-
tery module (see figure 10). For higher quantity of modules
reproduce the connection procedure among them.
Ŗ
All models can be installed in a 19" rack cabinet, keeping in
mind the height of each model:
Models up to 3 kVA, height of 2 units.
Battery module for models up to 3 kVA, height of 2 units.
Models from 4 to 6 kVA, height of 3 units.
Models of 8 and 10 kVA, height of 5 units.
Battery module for models from 4 to 10 kVA, height of 3
units.
Ŗ
To do this, proceed as follows:
Fix both adaptor angles "A" to the equipment and to the
battery module as rack, on their side, by means of the
supplied screws.
Put a UPS in a rack cabinet, it is needed to have the side
internal as support mode "C". In lack of them and under
request, a universal rails can be supplied as a guide, to
be installed by the end user. Make the assembling at the
required height, assuring the correct torque of the fixing
screws.
Face the equipment over the rails and enter it to the bottom.
Proceed in the same way for the battery module.
Depending on the weight of model of the equipment and
battery module, it is recommended to make the installa-
tion works by two persons.
Fix the equipment to the frame of the cabinet by means
of the screws "B".
Ŗ
Regarding the connections of the UPS with the battery
module in models up to 6 kVA, make the following steps, but
reading section 4.3.4 previously:
Connect the supplied earth joint cable "F", between the
UPS and battery module.
Remove the beautiful front cover of the equipment and
battery module, as it is described in section 4.2.5.2.
Take the extensible cable with connector "H" of the bat-
tery module and connect it with the "G" connector of the
equipment.
To connect it with other battery modules, there is the "J"
connector. Take the extensible cable with "H" connector
of the beside battery module and connect it to the "J" con-
nector of the previous one. Repeat the same steps for a
high quantity of modules.
"C"
"B"
"F"
"G"
"J"
"K"
"K"
"H"
Fig. 10.
19" rack cabinet assembling, with extended back up
time (battery module).
In the side of each front cover, there are the "K" trims as
hole to go the cables through it with the battery modules.
Break the needed trims to pass the connection bus.
Put the beautiful front cover back of the equipment and
battery module, as it is stated in section 4.2.5.2.