32
SSCBL-RPBL-IOM (10-22) 149159-C
INSTALLATION—CONTINUED
Venting/Combustion Air Connections (Model SSCBL)—Continued
Vent Terminal Options
Figure 23. Horizontal and Vertical Venting Options
Vertical Vent Terminal (Option CC2) Installation
•
Field-supplied components required for installation of the vertical vent kit are as follows:
a . Vent and combustion air piping in accordance with
b . Tapered vent pipe diameter reducers and/or increasers, as required
c . Thimble (not required if wall is of non-combustible construction)
d . Flashing
e . Sheet metal screws, tape, and sealant, as required
•
Factory-supplied components for installation of the vertical vent kit are listed in
.
VERTICAL (OPTION CC2)
HORIZONTAL (OPTION CC6)
Figure 24. Option CC2 Components
EXHAUST VENT TERMINAL ASSEMBLY
COMBUSTION AIR INLET ASSEMBLY
Table 17. Vertical Vent Terminal/Combustion Air Package (Option CC2) Components
PN
Description
Quantity
205896
Kit package
1
*
205885
1
110052
Exhaust vent terminal assembly (see
1
53330
Combustion air inlet assembly (see
1
207232
Concentric adapter box bracket
2
53335
High-temperature silicone sealant, tube
1
*
One (1) required for each furnace section .