REED
00 MODEL:
C50SS
TRAILER CONCRETE PUMP
OPER.
PAGE
19
•
If the delivery line will cross rebars, support must be considered for the pipe so that it
does not contact the rebar mat.
•
For best pumping results it is important to size the inside diameter of the pipe or
hose to that of the size of the aggregate in the concrete to be pumped. The general
rule is the inside diameter of the pump or hose shall be 3 to 4 times the size of the
largest aggregate in the mix. As an example:
1. Aggregate classified as 1 ½ inch (38mm) rock, 8 to 10% maximum content
by weight requires a 5 inch (127mm) diameter concrete delivery system.
2. Aggregate classified a 1 inch (25mm) rock, 10 to 15% maximum content by
weight, requires a 4 inch (100mm) diameter concrete delivery system.
3. Aggregate classified as ¾ inch (19mm)or smaller rock, 10 to 15% maximum
content by weight, requires a 3 inch (76mm) diameter concrete delivery
system.
•
For vertical concrete delivery system, the vertical pipe line should be anchored to the
building or other supporting structures every 10 ft (3m) of height.
PRE-PUMPING PREPARATIONS
Again we
REMIND
you to make sure the machine is in
PROPER WORKING CONDITION
.
One of the worst, and possibly the most expensive, situation to encounter is to begin
pumping and have a failure occur due to
NEGLIGENCE
of a thorough pre-operation
inspection.
STARTING THE PUMP
Before starting diesel engine, check the position of the following controls and functions:
•
That the
PUMP CYCLE
switch is
OFF
•
That the
VOLUME CONTROL
is
CLOSED
, screwed in.
•
That
the
AGITATOR
control lever is in
OFF
position.
•
Check flush box is filled that sufficient lubrication oil or water exists. Replace cover.
REVISION:
Summary of Contents for 00 C50SS
Page 12: ...REED 00 MODEL C50SS TRAILER CONCRETE PUMP OPER PAGE 11 REVISION...
Page 29: ...REED 00 MODEL C50SS TRAILER CONCRETE PUMP OPER PAGE 28 MODEL C50SS REVISION...
Page 36: ...REED 00 MODEL C50SS TRAILER CONCRETE PUMP MAINT PAGE 06 REVISION...
Page 37: ...REED 00 MODEL C50SS TRAILER CONCRETE PUMP MAINT PAGE 07 LUBE POINT LOCATIONS REVISION...
Page 50: ...REED 00 MODEL C50SS TRAILER CONCRETE PUMP MAINT PAGE 20 REVISION...
Page 55: ...REED 00 MODEL C50SS TRAILER CONCRETE PUMP MAINT PAGE 25 REVISION...
Page 59: ...REED 00 MODEL C50SS TRAILER CONCRETE PUMP MAINT PAGE 29 REVISION...
Page 60: ...REED 00 MODEL C50SS TRAILER CONCRETE PUMP MAINT PAGE 30 REVISION S TUBE CIRCUIT HYD DIAGRAM...
Page 63: ...REED 00 MODEL C50SS TRAILER CONCRETE PUMP MAINT PAGE 33 REVISION...
Page 66: ...REED 00 MODEL C50SS TRAILER CONCRETE PUMP MAINT PAGE 36 REVISION...
Page 67: ...REED 00 MODEL C50SS TRAILER CONCRETE PUMP MAINT PAGE 37 REVISION...
Page 72: ...REED 00 MODEL C50SS TRAILER CONCRETE PUMP MAINT PAGE 42 REVISION...
Page 76: ...REED 00 MODEL C50SS TRAILER CONCRETE PUMP MAINT PAGE 46 REVISION...