7 steps to complete your BlackMax installation:
1.
Transporting
2.
Positioning
3.
Solar Install
4.
Electrical connections
4.1. Solar
4.2. Battery
4.3. Load
4.4. Generator
4.5. Generator Auto-Start
4.6. MSB
4.7. Monitoring
5.
Turn ON/Commissioning
5.1. Turn ON
5.2. Shutdown
5.3. Commissioning
5.4. Fan Control Adjustment
6.
Monitoring and Communication
7.
Finalizing and Handover
Step 1.
Transporting
The BlackMax system is supplied on a pallet in one
of two configurations (just unit or kit) as shown on
right. It is fully set-up and ready to run. The system
weighs around 176kg with 3x lithium batteries and
should be handled with proper lifting equipment.
RedEarth’s BlackMax
comes fitted with two
handles to help with
handling. However, it is a heavy unit and should be managed with a
transportation device such as a hand trolley. This is available as an
option from RedEarth.
As a last resort, the lithium batteries can be removed and replaced once
the system is in position. Each Troppo battery module weighs 42kg and
should be lifted with the extreme caution.