LM05 SERIES II I&M MANUAL/EN/11.30.2010
35/89
This document and the information contained herein, is the exclusive property of R&M Materials Handling, Inc., and represents a non-public, confidential and proprietary trade secret that
may not be reproduced, disclosed to third parties, altered or otherwise employed in any manner whatsoever without the express written consent of R&M Materials Handling, Inc.
Copyright © (2010) R&M Materials Handling, Inc. All rights reserved.
7.5 Fall Stop Assembly
7.5.1 General
The slack fall stop is a safety stop, not a functional stop. The fall stop must be located at least six
(6.0) inches [150mm] from end of last chain link.
Figure 14. Installation of Slack Fall Stop
7.5.2 Removing fall stop (
Figure 14
)
1. Remove cotter pin (item 1).
2. Slide up the tube (item 2).
3. Remove the two fall stop halves (item 3).
4. Slide tube (item 2) off load chain.
7.5.3 Fall Stop Installation (
Figure 14
)
1. Slide tube (item 2) onto load chain.
2. Position two fall stop halves (item 3) on a chain link so that the fall stop will be at least 6 inches [150mm]
from end of load chain.
3. Slide tube (item 2) down over two fall stop halves (item 3).
4. Insert and secure cotter pin (item 1).