Possible mistakes in the work related to the maintenance phase of the flame:
Boiler operation, beside the functioning of the phase of flame maintenance, does not have
enough pellets for the start and work in normal mode.
Eliminating the cause of mistake:
1. Reduce the parameter T04, i.e. increase the frequency of conveyor and fan work in the
phase of idle work.
2. Increase the duration of the process time, ie. The parameter T05.
Too much of unburnt pellet when boiler starting its work.
Eliminating the cause of mistake:
1. Increase the parameter T04
2. Reduce the parameter T05
3. Reduce the fan power for the primary combustion in the maintenance phase – the parameter
Uc09.
8.5 Maintenance of boiler
TKAN boiler requires daily and periodic cleaning.
•
Daily cleaning refers to the area of the firebox of cast iron where by continuous ash
ejection providesa better electric heaters work,a better firewood burning, i.e. a
bigger amount of air through air channels in the gray casting. But even during the day
the ash begins to accumulate on the floor,and the space around the furnace. The
average parameter of 100 kg of pellets produce 1 KG of ashes in combustion process.
•
In every 3 to 7 days it is necessary to clean the space between the pipe grid for solid
fuel. Also it is necessary to clean the deposits on the walls of the firebox. By this we
provide a better transfer as one millimeter layer of tar and soot decreases the
conductivity by 5%.
•
Once in a month it is necessary to open the top cover for cleaning, remove the
turbulators and then from the whole area of the boiler the tar and soot should be
removed. All that is removed in this way, can be collected and taken away through
lower openings. For a 35-BIOmax exchanger tube cleaning is done by moving up and
down turbulators.
(see figure.17)
If, during the cleaning. In the boiler there appears the condensation it is necessary to collect the
condensed matter and the whole boiler inside should be coated by base means for cleaning or
else by means of water solution of constyruction lime. In this way the neutralization of acids is
carried out due to condensation.
Summary of Contents for BIOmax Series
Page 18: ...5 Šema vezivanja automatike ...
Page 21: ...7 Hidraulična šema ...
Page 54: ...5 Schematic connection of automation ...
Page 57: ...7 Hydraulic scheme ...
Page 74: ......