Commissioning
The 0985 Aquila model without TermoPID can be supplied either with water
coming from the tank or from the water mains. According to the type of supply,
proceed as follows.
Tank
-
Position the tank/service tap (
q
), underneath the machine, on tank.
-
Position the tank/service switch (
r
) on tank.
-
Fill the water tank (use drinking water, softened if possible).
Water supply:
-
Connect the mains water supply pipe to the fitting under the machine.
-
Position the tank/service tap (
q
), underneath the machine, on service.
-
Position the tank/service switch (
r
) on service.
1. Open the water tank lid (
k
), take out the tank (
l
) and fill with drinking water,
softened if possible (only for supply with tank).
2. Connect the machine to an electric socket, switch on the machine with the
general switch (
m
) in
ON
position, the green light (
n
) switches on.
3. The machine fills the boiler.
4. Activate the coffee brew group lifting the lever (
b
): deliver water from the
group to ensure that the circuit has filled correctly.
5. Wait until the machine reaches the working temperature indicated by the red
heating light
that switches on, then off (
o
)and the boiler gauge
pointer (
h
) that is to indicate a value between 1 Bar and 1,5 Bar.
When used for the first time, with the machine warmed, allow an
outlow of approx.0,5 litres of water to flush the delivery group
activating the coffee delivery.
Summary of Contents for MILANO 0980
Page 32: ...32 Ita lia no En gli sh Fr an a is D eu tsc h 0985 AQUILA E AQUILA PID...
Page 44: ...44 Ita lia no En gli sh Fr an a is D eu tsc h 0992 QM67 2 BOILER PID...
Page 54: ...54 Ita lia no En gli sh Fr an a is D eu tsc h 0995 VETRANO 2 BOILER PID...
Page 61: ...61 Ita lia no En gli sh Fr an a is D eu tsc h 995 VETRANO DOSATA 2 BOILER PID...