BES X installation manual
Scoring network
P/N: 400288005; Rev: L, 09/21
55
T.20.104 – 4HD/5HD-HUB installed on XLi pinspotters with low ceiling safety kit
A
Solid homerun cable
from Conqueror ro
P
server
4
/5HD
HD
HUB
Patch network
cables to other
4
-
units
HD HUB
or SLAVE
Scoring Network
switches
MAIN Scoring
NET switch
A
B
B
Patch network
cable from the main
Scoring Network
switch
4
/5HD
HD
HUB
With Xli pinspotters with the low ceiling safety kit, always install the 4HD/5HD-HUB unit and all other
devices to the panel located between each pair of pinspotters, as shown in the details A and B.
The MAIN Scoring NET switch has to be installed in the middle of the Scoring Network. For example, in a
8 lanes installation the MAIN Scoring NET switch has to be installed between the lane 4 and the lane 5.
Do
NOT
run any scoring system cable in the pinspotter conduits for any reason.
Keep the scoring system cables far away from any power cable.
Summary of Contents for 400288005
Page 1: ...P N 400288005 REV L 09 21...
Page 24: ...Electrical specifications BES X installation manual 14 P N 400288005 Rev L 09 21...
Page 94: ...Front Desk BES X installation manual 84 P N 400288005 Rev L 09 21...
Page 114: ...System first start up BES X installation manual 104 P N 400288005 Rev L 09 21...
Page 141: ...BES X installation manual Parts P N 400288005 Rev L 09 21 131...