Protective Grounding

In order to prevent electrical shock or fire, the frame of the 

module as well as any non-current-carrying metal parts of the 

system must be grounded. While this section provides some 

information about grounding the Q CELLS frames and modules, 

reference should be made to local statutes and regulations for 

specific requirements on grounding. The U.S. National Electrical 

Code addresses these issues in Article 250. A module with 

exposed conductive parts is considered to be in compliance 

with this standard only when it is either electrically grounded 

in accordance with the manufacturer’s instructions and the 

requirements of the National Electrical Code, ANSI / NFPA 70 

(2014-2017), or when the bonding means has been evaluated with 

this module to UL 2703.

Proper grounding is achieved by bonding all exposed non-

currentcarrying metal equipment to the appropriately sized 

equipment grounding conductor (EGC) or racking system that can 

be used for integrated grounding.

Q CELLS frames are protected from corrosion with an anodized 

coating, which has to be penetrated in order to ensure proper 

bonding. The different methods listed below are suggested 

methods for an appropriate bond between the frame and the 

EGC or racking system (that will have to be properly grounded). 

The method appropriate for any individual installation will depend 

on multiple factors.

Option A: Use of a grounding lug

A listed grounding lug can be bonded to the frame using the 

grounding holes pre-drilled in the frame. These holes are 

marked with a ground symbol, as shown below on the frame 

section drawing: To install the grounding lug, follow the specified 

instructions of the manufacturer. The grounding lug should be 

made of stainless steel or tin plated metals such as aluminum to 

avoid corrosion.

The grounding lug should be attached to the frame grounding 

hole using a stainless steel screw, toothed lock washer or KEPS 

nut (in order to penetrate the anodized layer) and backing nut. 

Care should be taken to avoid the use of grounding hardware of 

dissimilar metals, which may lead to corrosion.

Option B: Integrated grounding methods

The Q CELLS modules can be bonded with the racking system 

using UL1703 or UL2703 certified integrated grounding methods. 

The racking system will then have to be grounded so that the 

overall system is properly grounded. The listed racking system 

and grounding device should be installed in accordance with 

the manufacturers’ instructions. An example of such integrated 

grounding method is the use of a WEEB clip or Schletter plate 

between the module and the racking system, when mounting the 

module.

The WEEB washers are generally compatible with Q CELLS 

modules, however each combination module / racking system 

requires a specific WEEB washer size. Note that WEEB clips 

are intended for single use only; they must not be reused after 

removal or loosening. Refer to Wiley’s installation instructions for 

the specific use of WEEB washers.

An example of such integrated grounding method is the use of a 

washer recognized as meeting UL2703 requirements between 

the module and the racking system, when mounting the module. 

For example, WEEB washers are generally compatible with 

Q CELLS modules, however each combination module / racking 

system requires a specific WEEB washer size. Note that WEEB 

washers are intended for single use only; they must not be 

reused after removal or loosening. Refer to Wiley’s installation 

instructions for the specific use of WEEB washers.

4 Electrical connection

4.4 After installation

5 Grounding

  Ensure that all necessary safety and functional tests 

have been carried out according to applicable 

standards.

Note! Module damage may occur!

  Ensure that the plug connections are secured away 

from any water-channelling surface. 

  Integrate the system into the existing lightening 

protection system in accordance with the applicable 

local regulations.

Warning! Fire Risk!

  Do not use light concentrators (e.g. mirrors or lenses).

  Ensure that the cabling is not exposed and / or 

hanging and is protected from dirt, moisture and 

mechanical friction.

 

Dimensions shown are in inches.

0.177” (+0.008/-0)

±0.08

0.79”

0.47”

±0.08

PV Laminate

Backing Nut (Stainless Steel)

Toothed Lock Washer (Stainless 
Steel)

Grounding Lug (Stainless Steel 
or tin-plated metal)

Equipment 
Grounding 
Conductor

Aluminum 
Frame

Screw (Stainless Steel)

Summary of Contents for Q.PEAK DUO BLK-G10+ / HL Series

Page 1: ...Installation and operation manual Q PEAK DUO BLK G10 HL solar module series...

Page 2: ...The installer and solar module operator are responsible for compliance with all applicable statutory requirements and regulations The following regulations and standards must be upheld at all times d...

Page 3: ...ystem Your financial success depends on the fulfillment of these requirements Other applicable documents This installation manual is only valid in combination with the following technical information...

Page 4: ...tact corrosion Allows for stress free expansion and contraction due to temperature fluctuations Ensure that no additional forces are applied through the mounting system into the module except for the...

Page 5: ...ounting rails If connection cable runs between laminate and mounting it should be running at mounting rails position close to frame parts Modules bend under load Therefore sharp objects e g screws bal...

Page 6: ...ter into account when determining the maximum number of modules in the string Parallel Connection Modules may be damaged by the occurrence of reverse currents caused by module defects ground leaks or...

Page 7: ...nection cables or junction box Carry modules upright and horizontally as shown Note Module damage may occur Never step on modules Do not subject modules to any mechanical stress Do not allow any objec...

Page 8: ...electric arcs may result from the separation of a closed circuit These can result in life threatening injuries The danger increases when several modules are connected in series Please be aware of that...

Page 9: ...y only be performed by qualified and skilled personnel see page 3 Ensure correct polarity Use solar cables for the connection at the junction box outlet Only interconnect connectors of the same type a...

Page 10: ...n to avoid the use of grounding hardware of dissimilar metals which may lead to corrosion Option B Integrated grounding methods The Q CELLS modules can be bonded with the racking system using UL1703 o...

Page 11: ...t taking adequate security precautions Please commission a trade specialist NOTE Module surface damage may occur Remove snow and ice carefully without force e g with a very soft broom Do not scratch o...

Page 12: ...Installation manual solar modules Q PEAK DUO BLK G10 _HL_modules_series_2022 05_Rev01_NA HANWHA Q CELLS AMERICA INC 400 Spectrum Center Drive Suite 1400 Irvine CA 92618 USA EMAIL WEB TEL inquiry us q...

Reviews: