Replacing an inverter
Please use the original packaging if you return a device.
Decommissioning an old device:
No.
Action
1
Switch the DC disconnecter switch (1) on the underside of the device to
“OFF”.
2
Disconnect the AC grid connection (2) and verify absence of voltage.
3
Remove the PV plug-in connector
4
Remove the AC power plug (3) from the waste device.
5
Remove any earth connection (4) from the earthing bolt of the device
6
Remove all remaining plugs from the waste device.
The plugs must be re-connected to the replacement device in the same way.
Commissioning a new device:
No.
Action
1
Switch the DC disconnecter switch (1) on the underside of the device to
“OFF”.
2
Disconnect the AC grid connection (2) and verify absence of voltage.
3
If applicable attach the earth connection (4) to the earthing bolt of the device.
4
Attach the AC power plug (3) to the inverter.
5
Attach the DC plug-in connector to the inverter.
6
Attach all remaining plugs to the inverter. The plugs must be re-connected to the
replacement device in the same way as they were connected to the waste device.
7
Switch the AC grid connection (2) on again.
8
Switch the DC disconnecter switch (1) on the underside of the device to
“ON”.
9