ASSEMBLY
4.3 OPTIONAL STEP
4.3.1 ASSEMBLY OF THE RIDGE CONNECTOR IN
THE DIRECTION OF THE RAILS O
1
A pitch change / ridge on the roof can be built over up to a roof pitch of 1.5° without additional components. The prerequisite for
this is that the transition from base
C
to connecting base profile
D
runs exactly above the high point and can act as a “joint”. With
a roof pitch > 1.5°, the change in pitch must be covered with the ridge connector
O
1
.
PROCEDURE:
The first thing to do is to determine the ridge line. The main base profiles are then built up and, instead of the connecting base profiles
D
, the ridge connector
O
1
is installed. The order here is
A
C
B
C
D
C
B
C
O
1
C
D
C
…
B
C
A
. Ideally,
the structure should be built up evenly on both sides to prevent one-sided loading and thus slipping.
Finally, the topmost components main base profile
B
, base
C
, ridge connector
O
1
, base
C
, main base profile
B
, which are coupled
over the ridge, are each screwed in place with a total of eight M8x16 screws.
INFO
i
NOTE:
The location and position of the ridge connectors
O
1
can always be found in the current project report.