Installation Guide / ComT 2.0: 5°, 10° and 15°
18
Code-Compliant Planning and Installation Guide V1.0 - Complying with AS/NZS1170.2-2011 AMDT 2-2016
Figure 30
Figure 31
Figure 32
Figure 33
Once the grounding lug is attached to the rail,
insert U-Shape Copper Channel into the grounding
lug as shown in Figure 31. Strip earthing cable (the
maximum size is 10 mm
2
), insert the conductor into
the Copper Channel and tighten the bolt M6*14
with 5~6 N•m to ensure the earthing cable is tight.
Note: Please check the electrical resistance between
the rail and earthing cable conductor to ensure the
bonding is made.
Option 1
Fix the Grounding Lug into the top channel of the
Rail as shown in Figure 32.
Option 2
Fix the Grounding Lug at the side channel of Rail as
shown in Figure 33.
6. Grounding Lug Installation
5.5.3 Repeat the above steps to install other Front
and Rear Legs, and PV modules.
5.5.4 The installers must ensure panel clamps are
installed flush mounted to the panel frame and
apply correct torque value of clamp fastener as
shown in section 4.3.2.
It is required to install one Grounding Lug per row of rail. The recommended fasten torque of the bolt M8*25 is 16~20
N•m.
There are two options for Grounding Lug installation.
- Installation Instructions -