GATE CARE BEFORE OPERATION

Before adapting the machine to the gate, check the sliding, following the 

instructions below:

1st Step:

 Before installing the operator, check that the gate is in good mechanical 

condition, that is, opening and closing properly. Manually open the gate and note 

the effort required. This effort should be minimal along the entire length of the 

route.

2nd Step:

 Close the gate manually and check if the effort exerted was equal to the 

previous operation.

The gate must have a strong structure and, as much as possible, non-deformable. 

The pulleys must have a diameter consistent with the dimensions of the gate, be in 

perfect rolling condition and mounted so that the gate leaf has stability throughout 

its movement. We recommend pulleys with a minimum diameter of 120 mm.

The figures below represent the two types of rails and pulleys used. The system that 

uses a straight section (Picture A - angle) presents greater friction and consequently 

greater wear. The circular section (Picture B) allows for better gate displacement 

and less friction for the operator.

PICTURE A

PICTURE B

3rd Step:

 Check that the gate leaf does not get stuck in the opening and closing 

movement. The gate’s sliding rail must be perfectly straight, level, periodically free 

of any element or dirt that makes it difficult for the pulleys to slide along their 

entire length, as shown in the figure below.

INSTALLATION AND FIXING THE OPERATOR

Before installing the operator, remove all unnecessary cables and disable any 

equipment or system connected to the electrical network.

EQUIPMENT DIMENSIONS

The perfect functioning of this equipment depends on the instructions contained 

in this manual. To secure the equipment, proceed as follows:

1st Step:

 Check if the floor is firm enough so that the equipment can be screwed so 

that it is level. If you do not comply with the requirement, provide a concrete base, 

following the guidelines below:

Summary of Contents for DZ RIO

Page 1: ...l manual P30454 04 2022 Rev 0 Made by Motoppar Ind stria e Com rcio de Automatizadores Ltda Av Dr Labieno da Costa Machado 3526 Distrito Industrial Gar a SP CEP 17406 200 Brasil CNPJ 52 605 821 0001 5...

Page 2: ...equired on the equipment identification label Do not turn on the mains until the installation maintenance is completed Make the electrical connections of the command board always with the power grid t...

Page 3: ...SLIDING SLIDING SLIDING SLIDING MODEL THREE PHASE THREE PHASE THREE PHASE THREE PHASE RATED VOLTAGE 127V 220V 127V 220V 127V 220V 127V 220V NOMINAL FREQUENCY 60 Hz 60 Hz 60 Hz 60 Hz RATED POWER 340 W...

Page 4: ...use must be a flexible cable 3 x 0 75 mm 500 V according to the NBR standard NM 247 5 The power conductor of a product for external use must be a flexible cable 3 x 0 75 mm 500 V as per the standard I...

Page 5: ...The system that uses a straight section Picture A angle presents greater friction and consequently greater wear The circular section Picture B allows for better gate displacement and less friction for...

Page 6: ...EAF SIDE VIEW CONCRETE BASE 4th Step Pre align the operator to the gate positioning the rack over the gear and leaning the set against the gate Then mark the fixing holes in the floor or concrete base...

Page 7: ...mm GAP 2 mm 300 OR 400 mm 300 OR 400 mm 8th Step If the gate leaf is warped provide wedges to ensure rack alignment There are cases where the rack will need to extend the length of the leaf In this ca...

Page 8: ...REED This magnet will act as a closing limit switch MAGNET SUPPORT MAGNET SUPPORT REED SUPPORT UPPER VIEW GATE CLOSING 2nd Step Fully open the gate and place the other magnet support on the rack faci...

Page 9: ...maintenance it is necessary to completely disconnect the electrical network DEFECTS PROBABLE CAUSES CORRECTIONS Motor does not start does not move A Power off B Open blown fuse C Locked gate D Defecti...

Reviews: