0000100513/050719/C MDB GO | MDB PRO
9
ATTENTION
General installation instructions
• Remove the backing material
before
you put
the pointed positioning studs on the frame and
filter module. Try to avoid touching the sticky
seals with your fingers.
• Always use SealApplicator lubricant on the
sealing material before you connect any
component of the MDB system
8
.
By the use of SealApplicator you can slightly
shift the filter module to get the right position.
After approx. 60 seconds the lubricant is dry so
you cannot shift anymore.
• Install one filter module at a time. After
spraying, immediately position the filter module
or any other component
9
.
Vertical connection of filter modules
9x
4x
5x
+
<60 s
1
4
4x
3
5
2
4x
Horizontal connection of filter modules
9x
4x
5x
+
<60 s
1
4
4x
3
5
2
4x
Refer to Fig. IV on page 18 for instructions about
the assembly sequence.
Remove the filter lids and the round cover plates on
the back to have an easier access to the inside of
the filter modules for connection purposes.
The installation instructions that follow concern both
single and multiple stack MDB systems. Some
instructions apply to single or multiple stack MDB
systems only. This is clearly indicated in the text.
Single stack MDB
Multiple stack MDB
4.4.1 Filter module on frame
• Put the MDB-FRAME (A) in fully horizontal position.
8.
The seals are extremely adhesive; without the use of SealApplicator,
components might stick together in the wrong position and cannot be
disconnected without damage.
9.
After approx. 60 seconds SealApplicator lubricant loses its functions and you
cannot shift anymore. Therefore, do not install multiple filter modules or stacks
of filter modules. This takes simply too much time.
• Multiple stack MDB system only:
Put the other frame(s) (B) next to it.
Fig. 4.16
(±30 sec.)
8
a
7
(±30 sec.)
9
(±30 sec.)
1
2
3
4
5
6
C (6x)
A
B
D (6x)
E
(±30 sec.)
C (9x)
D (9x)
A
B
<30 s
<60 s
B
A
1
3
4
2
A (4x) B (2x)
A
A
A
A
B
B
Frames
• (1) Remove the backing material of the seals.
• (2) Put 4 positioning studs in the upper cage nuts of the
mounting frame (corner positions).
• (3) Spray SealApplicator lubricant on the seals.
• (4) Put the filter module
within 60 seconds
on the frame.
• (5) Put a locknut on the positioning studs and
tighten them.
Fig. 4.17
<60 s
1
2
4
4x
4x
3
5
<60 s
1
2
4
4x
4x
3
5
<60 s
1
4
4x
3
5
2
4x
9x
2x
Filter module on first frame
• Put studs in the remaining 2 cage nuts and tighten them
with a flange nut (B).
Fig. 4.18
(±30 sec.)
8
a
7
(±30 sec.)
9
(±30 sec.)
1
2
3
4
5
6
C (6x)
A
B
D (6x)
E
(±30 sec.)
C (9x)
D (9x)
A
B
<30 s
<60 s
B
A
1
3
4
2
A (4x) B (2x)
A
A
A
A
B
B
Position of studs
Multiple stack MDB system only:
• (1) Remove the backing material of the seals:
- on the frame
- on the vertical side of the filter module
• (2) Put 4 positioning studs in the upper cage nuts of the
mounting frame (corner positions).
• (3) Spray SealApplicator lubricant on the seals (of frame +
side of filter module)
10
.
10.
Start with the horizontal surfaces