SERVICE
24
L22-236 Rev. 2 (06/11)
5. Remove burner mounting screws, (2/burner)
using 5/16 hex bit.
6. Remove
burners.
7. Note: On split vat fryers it may be necessary to
bend up the outside tabs on the burner bracket
shield to allow removal of the outside burners.
8. Installation is reverse of removal. Be sure that
burner is properly seated on orifice spuds
when re-installing burner.
5.3.5. Gas Conversion
1. Note: On some fryers, burner replacement is
required when performing gas conversion. If
burner removal is required, remove burners
per Section 5.3.4.
2. Remove pilot assembly. See Section 5.3.3.
3. Remove gas supply tubing from pilot. Remove
pilot orifice and install new pilot orifice.
4. Remove front panel bezel, bottom rail, and
heat shield to gain access to burner orifices.
See Section 5.1.4
5. Remove burner orifice tips using 7/16” wrench.
Install new burner orifices
6. Reinstall pilot assembly.
7. If removed, reinstall main burners.
8. Remove gas valve regulator cap screw.
9. Remove regulator adjustment screw.
10. Remove regulator spring. Install new regulator
spring. Reinstall regulator adjustment screw
11. Install manometer at regulated gas pressure
tap. Ensure that there is adequate oil in fry
tank. Press I/O button to start fryer. Adjust
regulated gas pressure to specification for gas
being used.
12. Reinstall regulator cap screw.
13. Install Gas Conversion Label on inside door of
fryer.
WARNING! SHUT OFF APPLIANCE AND DISCONNECT ALL POWER
CONNECTIONS PRIOR TO STARTING ANY SERVICE WORK
WARNING! DISCONNECT APPLIANCE FROM GAS SUPPLY OR SHUT
MANUAL GAS VALVE PRIOR TO SERVICING GAS TRAIN