Start-up
Connect the conveying container to the silo outlet flap.
Lay out the conveying line between the cleaning machine and the conveying
container outlet.
To ensure that the system works optimally over long conveying distances,
the conveying line should not only be laid out flatly.
We therefore recommend that you create raises - e.g. at the hose coupling
by means of, for example, two pallets placed upright.
Connect the air hose from the conveying container to the compressor.
Connect the air hose from the compressor to the conveying container.
Connect the 10-pin control cable from the control box to the servo motor of
the flap.
Connect the control cable
(item no. 20 42 38 00) to the CEE panel-
mounted socket 3 x 16 A 12 h white, and
connect the injection hood to the rotary wing
sensor.