CF-F-Flansch
Applications for installing an CF-F to an CF-F flange are “Stud
screw with blind hole” and “Hexagon screw and clearance
hole”. The following items are needed: the particular set of
mounting material and a copper seal. Using asplinter shield or
protective screen is optional.
Don’t touch the copper seal with bare hands,
this may affect the sealings efficiency. See
that the sealing lip is not damaged.
☞
PLEASE NOTE
B
A
C
52
Hexagon screw and clearance hole
➡
If used: Insert the splinter shield and protective screen in
the high vacuum flange with the clamping lugs downward
(towards the pump).
➡
Bring the seal centric into the correct position.
➡
Connect the flanges via 2244 pieces of hexagon screws (M8)
with washers and nuts. The hexagon screws need to be
tightened revolving with a tightening torque of 22 ±2 Nm.
Control the torque afterwards, because of the sealing
material’s flowing a retightening of the screws may be
required.
B
A
C
55
Stud screw with blind hole
A
CF-F flange
B
Stud screw with washer and nut
C
Copper seal
Hexagon screw and clearance hole
A
CF-F-flange
B
Hexagon screw with washer and nut
C
Copper seal
1) Nut with flange.
➡
See that the sealing surface is not damaged.
➡
Flange the turbopump according to the drawing and the
component parts in your set of mounting material. Use 1122
screws and 2244 nuts.
➡
For a flange material having a strength of > 170 N/mm
2
and
a stud screw with clearance hole, the nuts must be
tightened crosswise in three steps.
Tightening torque: 10 Nm, 20 Nm, 38 ±3 Nm
B
A
C
D oder/or E
Stud screw and clearance hole
A
ISO-F flange
B
Stud screw with two nuts1)
C
Centering ring, coated
D
Splinter shield
E
Protective screen
Variant 3 - Stud screw and clearance hole
Stud screw with blind hole
➡
If used: Insert the splinter shield and protective screen in
the high vacuum flange with the clamping lugs downward
(towards the pump).
➡
Bring the seal centric into the correct position.
➡
Connect the flanges via 2244 pieces of stud screws (M8) with
washers and nuts. The stud screws need to be tightened
revolving with a tightening torque of 22 ±2 Nm. Control the
torque afterwards, because of the sealing material’s
flowing a retightening of the screws may be required.
C
Co
on
nn
ne
ec
cttiio
on
n n
no
om
miin
na
all--
D
De
essiig
gn
na
attiio
on
n
O
Orrd
de
err--n
nu
um
mb
be
err
d
diia
am
me
ette
err
DN 200 CF-F
Hexagon screw M8 with
PF 505 004 -T
washer and nut
(25 pieces1))
Stud screw M8 with
PF 507 004 -T
washer and nut
(34 pieces1))
Copper seal (5 pieces1))
PF 501 420 -T
or
copper seal silvered
PF 501 520-T
(5 pieces1))
Splinter shield2)
PM 016 321
Protective screen2)
PM 016 342
The components for installing to an CF-F flange are to be
ordered under the following numbers:
1) supplied pieces