TTD-03.1 Electromechanical Box Tripod Turnstile
15
To ensure accurate passage tracking when the turnstile is operated with an ACS, it is
recommended to create the passage area in such a way that the barrier arm turning in the direction
of movement must be at the angle of not less than 70° (Fig. 9).
Fig.9 Recommendations on creation of the passage area
8.2 Tools and equipment required for installation
•
1.2÷1.5kW hammer drill;
•
hard-alloy drill bits for anchor bolts sleeves, dia 16 mm;
•
Phillips head screwdriver №2;
•
Flat slot screwdriver No.2; No.5-150 mm);
•
Allen key S=6, S=8;
•
Horn-type and socket wrenches S17, S13, S10, S8, S7;
•
Knife
assembly;
•
Plumb-line and level;
•
Bail for electric raceway;
•
Slide caliper;
•
Measuring tape 2m.
Note:
It is allowed to use other testing equipment and measuring tools provided the equipment in
use ensures the required parameters and measurement accuracy.
8.3 Cable length
The maximum allowed length of the RC-panel / WRC / ACS controller cable is not more than 50m.
The maximum allowed length of the turnstile power supply cable depends on the cable cross-
section and should be:
•
for cable with 0.2 mm
2
cross-section (AWG 24) ...................................................... max 10 m
•
for cable with 0.75 mm
2
cross – section (AWG 18) ................................................... max 25 m
•
for cable with 1.5 mm
2
cross – section (AWG 16) ..................................................... max 50 m
8.4 Installation procedure
Note!
The manufacturer shall not be liable for any damage caused in the result
of improper installation and declines any claims arising thereof in case
if the installation is not in compliance with the instructions provided in this Manual.
Recommendations on how to prepare mounting holes in the foundation (the mounting surface) are
given with regard to metal anchor bolts for solid concrete floors or similar foundations ("SORMAT"
PFG IH10 16x60). Use relevant mounting hardware for installation on different foundations.
1. Unpack the turnstile, check the completeness of the delivery set as per Chapter 3 of the
Certificate.