9. Regeneration Day Override

This program step sets the maximum amount of time (in days) 

the unit can be in service without a regeneration.

•  Press the Shift button to select the digit you want to modify.
•  Press the Up or Down buttons to adjust this value.
•  Press the Extra Cycle button.

10. Regeneration Time

This program step sets the time of day for the regeneration to 

occur in delayed systems.

•  Press the Shift button to select the digit you want to modify.
•  Press the Up or Down buttons to adjust this value.
•  Press the Extra Cycle button.

11. Regeneration Cycle Step Programming

This program step programs the Regeneration Cycle step 

times 1 through 6. Please refer to the chart below for 

regenerant flow default cycle steps and times.

Cycle

Time

1 Back Wash

10 Minutes

2 Brine & Slow Rinse

1 Hour

3 Rapid Rinse

10 Minutes

4 Brine Tank Fill

12 Minutes

5 N/A

N/A

12. Auxiliary Relay Output

The next two displays are part of a series of settings used to 

program the optional relay output. The first setting turns the 

output on/off during regeneration only. The second turns the 

output on during service only, every time a set volume of water 

used has accumulated.

NOTE:   When auxiliary outputs are in the OFF (default) 

setting, press the Up or Down buttons to set the first 

setting. Then press the Extra Cycle button to advance 

to the second setting.

MASTER PROGRAMMING MODE 

CONTINUED

13. Timed Auxiliary Relay Output Window (Start & End 

Time Setting)

This option setting consists of two displays. The first display 

sets the turn-on time of the output, referenced to the start 

of the first regeneration cycle. The second display sets the 

output turn-off time, referenced again to the start of the first 

regeneration cycle. An OFF setting cancels this setting. All 

settings are in minutes and output timing is synchronized with 

regeneration cycle timing.

Start Time:

 Any time during regeneration.

End Time:

 At start time, and anytime during the  

regeneration cycle.

14. Chemical Pump Auxiliary Relay Output Window

This option setting consists of two displays. The first display 

sets the volume of water flow at which the output turns on. 

The second display sets the on time (in seconds) of the output.

•  Activate output after volume set is reached.
•  Press the Shift button to select the digit you want to modify.
•  Press the Up or Down buttons to adjust this value.
•  Press the Extra Cycle button.

15. Flow Meter Size

This program step sets the size of the flow meter.

•  Press the Up or Down buttons to adjust this value.
•  Press the Extra Cycle button.

16. Maximum Flow Rate

This program step sets maximum flow rate of the generic  

flow meter.

•  Press the Shift button to select the digit you want to modify.
•  Press the Up or Down buttons to adjust this value.
•  Press the Extra Cycle button.

17. Pulses per Gallon/Liter

This program step sets the pulses per gallon/liter for generic 

flow meters.

•  Press the Shift button to select the digit you want to modify.
•  Press the Up or Down buttons to adjust this value.
•  Press the Extra Cycle button.

18. End of Master Programming Mode

Summary of Contents for FLECK 7000XTR

Page 1: ...www pentairaqua com FLECK 7000XTR SERVICE MANUAL...

Page 2: ...be installed by a plumbing professional This unit is designed to be installed on potable water systems only This product must be installed in compliance with all state and municipal plumbing and elect...

Page 3: ...ss __________Grains French Degrees German Degrees PPM 7 Capacity Safety Factor A Zero B __________ 8 Volume Override __________ Gallons or M3 9 Regeneration Day Override A Off B Every__________Days 10...

Page 4: ...to local plumbing codes 3 Cut the 1 05 inch 2 6 cm distributor tube flush with the top of the tank A Deburr the outside of the tube B after cutting Lubricate the o ring C with non petroleum based grea...

Page 5: ...eration time has been reached Meter Delayed Weekly Reserve A Volume remaining has been depleted to the weekly variable reserve volume and B the regeneration time has been reached Volume Override Immed...

Page 6: ...ay Regeneration Day Override Feature If the Day Override option is turned on and the valve reaches the set Regeneration Day Override value the Regeneration Cycle starts at the programmed regeneration...

Page 7: ...FLECK 7000XTR Service Manual 7 MASTER PROGRAMMING MODE FLOW CHART CONTINUED...

Page 8: ...tra Cycle button 2 Valve Type This program step selects the valve type Press the Up or Down buttons to adjust this value Press the Extra Cycle button 3 Regenerant Flow This program step selects how th...

Page 9: ...y Output Window Start End Time Setting This option setting consists of two displays The first display sets the turn on time of the output referenced to the start of the first regeneration cycle The se...

Page 10: ...types 3 Set Regeneration Day Override To turn on and set the days press the Down button Press the Shift Up and Down buttons to move the cursor and change the value of the numbers Press the Extra Cycl...

Page 11: ...the Extra Cycle button 2 Peak Flow Rate This program step displays the peak flow rate 1 minute average since the last regeneration Press the Extra Cycle button 3 Totalizer This program step displays t...

Page 12: ...ar Main 7 1 40704 Cam Brine Downflow 8 1 40979 Plate Lower Support 9 1 61635 01 Cover Assy 7000 II Black 1 61634 01 Cover Assy 7000 II Gray 10 1 40980 Backplate 7000 11 4 13602 Screw Phil Rd Hd 6 32 x...

Page 13: ...FLECK 7000XTR Service Manual 13 CONTROL VALVE ASSEMBLY 61500 7000EXP REV C...

Page 14: ...C Assemblies DLFC Size GPM 61455 00 3 4 inch Blank 61455 17 3 4 inch 1 7 61455 20 3 4 inch 2 0 61455 24 3 4 inch 2 4 61455 30 3 4 inch 3 0 61455 35 3 4 inch 3 5 61455 40 3 4 inch 4 0 61455 45 3 4 inch...

Page 15: ...ch BSP w O ring 3 2 41242 01 Connector Assy 1 inch 1 4 inch Sweat w O ring 41243 01 Connector Assy 1 1 4 inch 1 1 2 inch Sweat w O ring 4 2 40576 Clip H Plastic 7000 5 1 40951 O ring 220 Not Shown 1 6...

Page 16: ...LECK 7000XTR Service Manual 2310 SAFETY BRINE VALVE Item No QTY Part No Description 1 1 60014 Safety Brine Valve Assy 2310 2 1 60068 30 Float Assy 2310 w 30 inch Rod 3 1 60002 34 Air Check 500 42112 R...

Page 17: ...Flashing blinking display Power outage has occurred Either wait 5 minutes for blinking to stop or press any key on the keypad Unit not responding after going into regeneration Verify the unit is confi...

Page 18: ...system Remove piston and clean control Loss of mineral through drain line Air in water system Assure that well system has proper air eliminator control Check for dry well condition Improperly sized dr...

Page 19: ...ts and reset reserve capacity to provide additional reserve Meter is not measuring flow On Mechanical Meter Check with meter checker kit If volume is not registering check the meter cap and impeller f...

Page 20: ...REV A 41121 REV A Backwash Position 40988 REV A 41121 REV A Brine Position 40988 REV A 41121 REV A Slow Rinse Position 40988 REV A 41121 REV A Second Backwash Position 40988 REV A 41121 REV A Rapid R...

Page 21: ...t board align notches on left side of board with flexible finger on power head Apply pressure to left while rotating the board back 42554 REV A 2 When all the way down snap the circuit board into plac...

Page 22: ...22 FLECK 7000XTR Service Manual DIMENSIONAL DRAWINGS 61500 7000XTR LNE REV A METER FLOW DATA TR18753 Softener TR18688 Filter 41140 02 REV A...

Page 23: ...FLECK 7000XTR Service Manual 23 INJECTOR FLOW DATA TR18755 REV B...

Page 24: ...emarks and logos are the property of their respective owners Because we are continuously improving our products and services Pentair reserves the right to change specifications without prior notice Pe...