PV1000agri pellet burner
p
30/ 50
Operation and maintenance
Statuses and parameters
DK9401A1
www.pelltech.eu
End Blow
Pellet coals in burning chamber is burned, flame has disappeared
Waiting
Wait signal from boiler thermostat
Waiting
In this status, the burner is waiting signal from boiler thermostat. There is no limit time for waiting
status. Only internal feeder is working periodically at “Waiting” time – ½ rotations after every 2 minutes.
When signal comes from the thermostat, burner will go to “Testing”.
Testing
At “Testing” time, burner integrity and important device functioning is checked.
Table 4 List of tests in TESTING status
Test name
Par nr.
Value
Unit
Test conditions
Battery voltage
-
22
V
Battery loading is turned OFF and feeder is turned
ON - voltage must be greater than 12V
Feeder current
Par 46 3..6
A
Feeder is turned ON – feeder current must be
smaller than Par 46
Draft
Par 62 +10
Pa
All fans are turned on. Draft must be under Par 62
Primary fan
Par 4
38
rot
Fan must rotate faster than 35rot = 38 (Par4) - 3
Secondary fan
Par 4
38
rot
Fan must rotate faster than 35rot = 38 (Par4) - 3
Cleaning
In “Cleaning” cycle, the linear actuator moves the grates and pushes out from burning chamber the ash
and residues. The cleaning cycle has been divided into 3 steps:
1. Grates are pulled fully in to actuator end limit.
2. Grates are pushed fully out to actuator end limit.
3. Grates are pulled in, actuator works 4 seconds.
Table 5 Cleaning parameters
Par name
Par nr.
Value
Unit
Test conditions
Cleaning cycle
interval
Par 48 0...250 min
„Burning“ time between „Cleaning“ cycles. If 0
then cleaning is turned off. If burned longer then
2x Par 48 then forced cleaning is made.
Actuator max.
current
Par 47 0.2..6 A
Actuator maximum current level. If greater, then
actuator is stopped and cleaning cycle is started
Summary of Contents for PV1000agri
Page 1: ...PV1000agri pellet burner User manual POOLELI DRAFT DK9401A1 ...
Page 24: ...PV1000agri pellet burner p 23 50 Installation Electrical connections DK9401A1 www pelltech eu ...
Page 25: ...PV1000agri pellet burner p 24 50 Installation Electrical connections DK9401A1 www pelltech eu ...
Page 26: ...PV1000agri pellet burner p 25 50 Installation Electrical connections DK9401A1 www pelltech eu ...