3.7 Commissioning
Prior to the initial start-up of the burner make sure that:
The burner is connected to the boiler
The boiler thermostat is installed and is functioning properly
The feeding auger of the burner is installed and connected to the burner
The smoke duct is connected to the chimney, the dampers for smoke gases are open and there is
sufficient draught. When the burner is operating, the negative pressure inside the furnace must
stay between 5-20 Pa
Sprinkler system is connected and pressure switch connected to safety circuit (chapter 3.3).
Phase and neutral wires in power cable are connected properly.
.....................................
Summary of Contents for PV1000agri
Page 1: ...PV1000agri pellet burner User manual POOLELI DRAFT DK9401A1 ...
Page 24: ...PV1000agri pellet burner p 23 50 Installation Electrical connections DK9401A1 www pelltech eu ...
Page 25: ...PV1000agri pellet burner p 24 50 Installation Electrical connections DK9401A1 www pelltech eu ...
Page 26: ...PV1000agri pellet burner p 25 50 Installation Electrical connections DK9401A1 www pelltech eu ...