Caution

 

 

During the following set-up instructions, be ready to STOP the drive should the motor try to overspeed. 

 

3.8 

Set the speed potentiometer to 5% (0.5V at terminal A8). 

 

3.9 

Refer back to 3.1 to display the CONFIGURE DRIVE menu. Slowly increase the MAIN 
CURR.LIMIT parameter towards a maximum

 

of 20%. At some point the motor will begin to 

rotate as the parameter value is increased.

 

The motor speed will

 

settle at 5%

 

of full speed. 

If the motor is loaded it may require more than 20% current limit to turn the motor. 

3.10 

Stop the drive by opening C3.  Now Autotune the drive. 

 

 

4: Autotuning 

This process tunes the drive to the connected motor. Initial conditions must be: 

  Main contactor open, i.e. terminal C3 = 0V 

 

  Program Stop (terminal B8), Coast Stop (terminal B9) 

and Enable (terminal C5) high, i.e. 24V. 

  No field voltage: Autotune automatically quenches the 

(default) internally supplied field.  

4.1 

Set AUTOTUNE to 
ARMATURE. 

4.2 

Close the main contactor (apply the "Start/Run" 
command to C3) to begin the Autotune. 

 

The keypad displays “Autotuning” during the process. When Autotune is complete (after approximately 10 seconds), 
the main contactor is opened and the AUTOTUNE parameter is reset to OFF. Ensure that "Enable" (C5) is OFF.

 

4.3 

Perform a PARAMETER SAVE now

. Refer back to 

3.3

 for how to do this. 

 

The drive is powered-up and operating using Armature Volts Feedback.

 

Summary of Contents for DC590C Series

Page 1: ...that You have read and understood the Safety Information provided separately I S S U E 1 Q Qu ui ic ck kS St ta ar rt t WARRANTY Parker SSD Drives warrants the goods against defects in design material...

Page 2: ...air clearances to be maintained above and below drives and other equipment additive when two units are mounted together Overall Dimensions Fixing Centres Frame Current Rating A Weight Kg lbs Width Hei...

Page 3: ...em of more than one drive connect all clean earth rails together and only connect to the dirty earth rail 2 at one point Motor Earth Ground Connect an earth ground wire to the motor from the dirty ear...

Page 4: ...t Breaker 9 3 Power Supply Cable 10 Terminal Rail 11 Dirty Earth Ground Rail A 1 Pole MCB B Control Transformer C 2 Pole MCB D Fan Fuses E Motor Overload Protection F Emergency Stop Relay G Double Ins...

Page 5: ...ust be closed for the drive to run Speed Demand Uni directional A1 A4 B3 The 10K potentiometer adjusts the speed setpoint Zero speed Terminal A1 0V input Maximum forward speed 100 Terminal B3 10V inpu...

Page 6: ...the Drive Motor Field D3 F D4 F Connect shield between motor and earth rail These terminals provide an internal motor field supply fused by 10A fuses If the motor has no field connections is a permane...

Page 7: ...8 Disconnect the load from the motor shaft if possible If there is any doubt about the integrity of a particular installation insert a high wattage resistor i e fire elements in series with the motor...

Page 8: ...tting a higher value than this results in 0A Armature Voltage VA CAL Set this using the 4 way switch SW7 The switch sets voltage according to the table The illustration shows a VA CAL setting of 200V...

Page 9: ...the Start Run command from C3 The main 3 phase contactor should open and remain de energised IMPORTANT The main contactor should never be operated by any means other than the drive s internal controls...

Page 10: ...Terminal A1 0V input Check that 3 phase mains is applied to the power terminals L1 L2 and L3 Check the correct field voltage appears between the field output terminals D3 and D4 This is high voltage...

Page 11: ...4 Autotuning This process tunes the drive to the connected motor Initial conditions must be Main contactor open i e terminal C3 0V Program Stop terminal B8 Coast Stop terminal B9 and Enable terminal...

Page 12: ...ions below to make the installation application specific CHAPTER 3 Connection Diagrams Control Connections Optional Equipment CHAPTER 4 Selecting Speed Feedback Initial Start up Routine the full routi...

Page 13: ...RM VOLTS FBK 1 ANALOG TACH 2 ENCODER 3 ENCODER ANALOG for Parker SSD Drives use Refer to SPEED LOOP ENCODER LINES 24 10 to 5000 The number of lines must be set to match the type of encoder being used...

Page 14: ...available is 200 for 10 seconds 150 for 30 seconds Power Supply Details 3 Phase Supply 3 phase 50 60Hz earth referenced TN and non earth referenced IT Operating Suppy Tolerance 10 Voltage Ranges 220 t...

Reviews: