background image

Drive Set-Up 

IMPORTANT

 

You must not exceed the maximum drive and motor ratings. Refer to the Product Code or rating label, 

and the motor rating plate 

The instructions are written in logical order. Complete each stage successfully before progressing to the next. 

This simple start-up routine assumes that: 

  The Drive is direct from the factory and thus using all factory default settings 

  You know how to operate and navigate the Man-Machine Interface (MMI) – display 

  The drive's control terminals are wired as shown in the Installation diagram 

  This simple set-up uses ARMATURE VOLTAGE (default setting) as the speed feedback method 

1: Pre-Operation Checks 

Completely disconnect the drive before point-to-point checking with a buzzer, or when checking insulation with a Megger.

 

Prepare to energise the drive and system as follows:

 

 

ISOLATE THE DRIVE 

using branch circuit protection or circuit breaker (

8

)

 

  Disconnect the load from the motor shaft, if possible

 

  If there is any doubt about the integrity of a 

particular installation, insert a high wattage resistor, 
i.e. fire elements, in series with the motor armature

 

Initial checks before applying power:

 

  Mains power supply voltage is correct for drive 

  Motor vent fan is connected correctly for direction of 

rotation 

  Auxiliary power supply voltage is correct for drive 

and integral fans (110A-270A) 

  Motor is of correct armature voltage and current rating 

  Check for damage to equipment 

  Check that cooling fans are intact and free from 

obstruction (110A-270A) 

  Check all external wiring circuits - power, control, 

motor and earth connections 

  Check for loose ends, clippings, drilling swarf etc. lodged in the Drive and system 

Ensure the safety of the complete system before the drive is energised:

 

  Ensure that rotation of the motor in either direction will 

not cause damage or injury 

  Ensure that other equipment will not be adversely 

affected by powering up 

  Ensure that nobody else is working on another part of the system which will be affected by powering up 

Summary of Contents for DC590C Series

Page 1: ...that You have read and understood the Safety Information provided separately I S S U E 1 Q Qu ui ic ck kS St ta ar rt t WARRANTY Parker SSD Drives warrants the goods against defects in design material...

Page 2: ...air clearances to be maintained above and below drives and other equipment additive when two units are mounted together Overall Dimensions Fixing Centres Frame Current Rating A Weight Kg lbs Width Hei...

Page 3: ...em of more than one drive connect all clean earth rails together and only connect to the dirty earth rail 2 at one point Motor Earth Ground Connect an earth ground wire to the motor from the dirty ear...

Page 4: ...t Breaker 9 3 Power Supply Cable 10 Terminal Rail 11 Dirty Earth Ground Rail A 1 Pole MCB B Control Transformer C 2 Pole MCB D Fan Fuses E Motor Overload Protection F Emergency Stop Relay G Double Ins...

Page 5: ...ust be closed for the drive to run Speed Demand Uni directional A1 A4 B3 The 10K potentiometer adjusts the speed setpoint Zero speed Terminal A1 0V input Maximum forward speed 100 Terminal B3 10V inpu...

Page 6: ...the Drive Motor Field D3 F D4 F Connect shield between motor and earth rail These terminals provide an internal motor field supply fused by 10A fuses If the motor has no field connections is a permane...

Page 7: ...8 Disconnect the load from the motor shaft if possible If there is any doubt about the integrity of a particular installation insert a high wattage resistor i e fire elements in series with the motor...

Page 8: ...tting a higher value than this results in 0A Armature Voltage VA CAL Set this using the 4 way switch SW7 The switch sets voltage according to the table The illustration shows a VA CAL setting of 200V...

Page 9: ...the Start Run command from C3 The main 3 phase contactor should open and remain de energised IMPORTANT The main contactor should never be operated by any means other than the drive s internal controls...

Page 10: ...Terminal A1 0V input Check that 3 phase mains is applied to the power terminals L1 L2 and L3 Check the correct field voltage appears between the field output terminals D3 and D4 This is high voltage...

Page 11: ...4 Autotuning This process tunes the drive to the connected motor Initial conditions must be Main contactor open i e terminal C3 0V Program Stop terminal B8 Coast Stop terminal B9 and Enable terminal...

Page 12: ...ions below to make the installation application specific CHAPTER 3 Connection Diagrams Control Connections Optional Equipment CHAPTER 4 Selecting Speed Feedback Initial Start up Routine the full routi...

Page 13: ...RM VOLTS FBK 1 ANALOG TACH 2 ENCODER 3 ENCODER ANALOG for Parker SSD Drives use Refer to SPEED LOOP ENCODER LINES 24 10 to 5000 The number of lines must be set to match the type of encoder being used...

Page 14: ...available is 200 for 10 seconds 150 for 30 seconds Power Supply Details 3 Phase Supply 3 phase 50 60Hz earth referenced TN and non earth referenced IT Operating Suppy Tolerance 10 Voltage Ranges 220 t...

Reviews: