Monitoring and Testing
5-22
3162-A2-GB20-40
August 2000
Starting a Payload Loopback
The Payload Loopback command (PLB) loops the received signal on the network
interface back to the network. The signal is looped back as close to the DTE
Drop/Insert (DSX-1) port as possible (after it has passed through the framing
circuitry of the DSU/CSU). Framing CRCs and BPVs are corrected.
496-14316-02
CSU
DSU
NETWORK
INTERFACE
DTE
(DSX-1)
ALL 1s
PLB
PORT 1
PORT 2
ALL 1s
ALL
1s
"
Procedure
To perform a Payload loopback:
1. From the Main Menu screen, select Test.
2. From the Test screen, select Network & DTE Tests.
3. For the Payload Loopback command (under Local Loopbacks), select Start.
Starting a DTE Loopback
The DTE Loopback command (DLB) loops the received signal on the DTE
Drop/Insert (DSX-1) port back to the DTE without change.
496-14317-02
CSU
DSU
NETWORK
INTERFACE
DTE
(DSX-1)
DLB
PORT 1
PORT 2
ALL 1s
"
Procedure
To perform a DTE loopback:
1. From the Main Menu screen, select Test.
2. From the Test screen, select DTE Tests.
3. For the DTE Loopback command (under Local Loopbacks), select Start.
Summary of Contents for 3162
Page 1: ...ACCULINK 3162 DSU CSU USER S GUIDE Document No 3162 A2 GB20 40 August 2000 ...
Page 12: ...Contents vi 3162 A2 GB20 40 August 2000 This page intentionally left blank ...
Page 16: ...About This Guide x 3162 A2 GB20 40 August 2000 This page intentionally left blank ...
Page 42: ...Operation 3 16 3162 A2 GB20 40 August 2000 This page intentionally left blank ...
Page 64: ...Configuration 4 22 3162 A2 GB20 40 August 2000 This page intentionally left blank ...
Page 94: ...Monitoring and Testing 5 30 3162 A2 GB20 40 August 2000 This page intentionally left blank ...
Page 186: ...Equipment List G 2 3162 A2 GB20 40 August 2000 This page intentionally left blank ...