SMARTZONE UPS INSTALLATION MANUAL
37
Figure 54: Reinstall the EBP Battery Baffle
c. Reinstall the faceplate on the EBP, by aligning the front panel latches with the
holes in the front of the unit and snapping the faceplate onto the front of the
EBP. Should have a positive snap of the latches on the faceplate.
Two-Post Racks
Additional hardware is required for installation in a standard EIA two-post rack with
threaded mounting holes. A SRM19CM3 rack mount shelf would need to be used for
this mounting technique. Please refer to the
Panduit Rack Mount Shelves specification
on the Panduit website for the specifications on this shelf to be used with each unit.
CAUTION
⚫
The units are heavy. Removing the units from its carton requires
a minimum of two people.
⚫
The 3-phase EBP (UVP480) cannot be mounted in a two-post
rack, there is no shelf to support the weight of this unit. The
weight of this unit would also make the two-post rack unstable.
⚫
If installing optional EBP(s), make sure to install the EBP(s)
directly below the UPS so that all wiring between the units can
use the wiring provided with the units.
⚫
The unit is not secured to the rack with this mounting technique,
the unit is just set on top of the shelf.
Note:
Mounting shelves are required for each individual unit to
avoid exceeding the capacity of the shelf.
Tower
The tower mounting is not the preferred recommended mounting technique for the UPS,
EBP and MBS units. However, the mounting hardware for this technique is provided
with most units. The 3-Phase UPS and EBP unit should not use this mounting technique