63
Installation Manual
Operation and Display Panel
To Install, Service or Disconnect (Shutdown) Equipment
(Overview): How to Turn the System Off
Installation and service of this equipment includes risk of electric shock.
1. Initiate External Solar PV Rapid Shutdown (If installed)
2. Turn OFF the Main Switch located outside the inverter enclosure on
the left side
3. Turn off the battery breaker located inside the Distribution Box
behind the thumb screw latched access door
4. (DC Coupled only) Turn off the PV Switch located outside the inverter
enclosure on the left side
5. Turn off all AC breakers located inside the Distribution Box behind
the thumb screw latched access door
6. Allow five minutes for all sources of supply to discharge
7. Check that AC and DC voltages are at a safe level.
8. Access to the wiring requires opening the access door using the
thumb screw and removing the four screws on the Inverter wire
compartment cover.