VZR.248100.000 IG
K-14 Swing gate
Installation Guidelines
8
4
INSTALLATION AND DE-INSTALLATION OF THE PRODUCT
4.1 Required equipment
Equipment used for the product installation:
1)
Electric perforating machine;
2)
16 mm carbide drill bit for drilling anchor holes in the floor (recommended anchor:
SORMAT PFGES10 М10-60);
3)
hexagon socket screw wrench S6;
4)
cross screwdriver;
5)
plumb or level;
6)
steel shims for products leveling.
4.2 Product installation
ATTENTION:
CAREFULLY READ THIS SECTION OF THE MANUAL
BEFORE MOUNTING THE PRODUCT.
ATTENTION:
IT IS RECOMMENDED TO MARK MOUNTING HOLES
BY MATCHING TO HOLES OF FLANGE OF POST BASE OF THE GATE
WITH ALREADY INSTALLED LEAF.
4.2.1
Prepare horizontal platform at the product installation site.
4.2.2
Prepare channel or cable duct from the installation site to power
supply unit and, if required, to ACS and security and fire alarm system connection
point.