IG-123-EN version 11; 23/07/2021
62
Operations sequence
General instructions
cpg
.0: GIS medium-voltage switchgear,
gas insulated, up to 40.5 kV,
in accordance with IEC Standard
Disconnection
1.
Press the "0" pushbutton to disconnect the circuit-
breaker.
Figure 7.62.
Circuit-breaker opened indicator
2.
Insert the lever in the earthing switch's actuating
shaft. Then turn 90º ANTI-CLOCKWISE. Check that the
earthing switch status indicator shows opened.
Figure 7.63.
Earthing switch opening sequence
Summary of Contents for velatia cpg.0
Page 79: ......