IG-123-EN version 11; 23/07/2021
21
General instructions
cpg
.0: GIS medium-voltage switchgear,
gas insulated, up to 40.5 kV,
in accordance with IEC Standard
Installation
6. Installation
6.1. Unpacking the equipment
The
cpg
.0 switchgear is supplied protected with a plastic
cover.
On receiving the equipment, check that the goods
supplied correspond to the order and associated
documentation. If this is not the case, contact
Ormazabal
immediately.
The disassembly process for the equipment is as follows:
1.
Using a blade, cutter or similar tool, cut the cellophane
the cubicle is wrapped in.
2.
Remove the cellophane.
3.
Detach the white polystyrene corner pieces.
4.
Unscrew the fi xings between the base and the pallet.
5.
Dispose of any waste in an environmentally friendly
manner.
It is advisable to make a visual inspection of the
equipment to check whether it has suff ered any damage
in transit. If damaged, contact
Ormazabal
immediately.
6.2. List of assembly materials supplied
A box is supplied along with the
cpg
.0 switchgear with all
the material necessary for installation and correct operation.
Depending on the cubicles which form part of the supply,
the assembly materials delivered will be some of the
following:
1.
Spring charging and actuating levers.
2.
Interconnection busbars and busbar compartment
enclosure elements.
3.
Earthing bars.
4.
Side trim panels.
5.
Medium-voltage fuses (if applicable).
6.
Nuts and bolts.
7.
Alcohol and paper roll.
Ensure the box contains the elements indicated in the
materials list provided with the supply. If it does not,
contact Ormazabal.
Summary of Contents for velatia cpg.0
Page 79: ......