Version 1.0.5 - 2020-12-09
24
Translation of original instructions
TX4414
GB
T
X
4414
_GB
_3.
fm
3.2
Delivery
INFORMATION
The machine is pre assembled. It is delivered in a transport box. After the unpacking and the
transportation to the installation site it is necessary to mount and assemble the individual com-
ponents of the machine.
Check the status of the machine immediately upon receipt and claim possible damages at the
last carrier also if the packing is not being damaged. In order to ensure claims towards the
freight carrier we recommend you to leave the machines, devices and packing material for the
time being in the status at which you have determined the damage or to take photos of this sta-
tus. Please inform us about any other claims within six days after receipt of delivery.
Check if all parts are firmly seated.
3.3
Unpacking
Install the machine close to its final position before unpacking. If the packaging shows signs of
having possibly been damaged during transport, take the appropriate precautions to prevent
the machine being damaged when unpacking. If damage is discovered, the carrier and/or ship-
per must be notified immediately so the necessary steps can be taken to register a complaint.
Inspect the machine completely and carefully, making sure that all materials, such as shipping
documents, manuals and accessories supplied with the machine have been received.
Dismantle the cover and side parts of the box.
Disassemble the clamping bolts which are used to fix the machine on the pallet.
3.4
Lifting the machine
3.4.1
Forklift
Put 2 wooden beams on the forks.
Lift the lathe from the rear site with the forklift on machine bed.
The machine can be lifted underneath
the machine substructure using a forklift
truck.
2.5 t
2.5 t